PP-0174: Complete return risers

Task Details

taskIdPP-0174
sourcePlant Head Email / Commissioning Addition
workstreamHVAC / Clean Room
areaClean room
equipmentSystemHVAC System
capacitySize
activityCategoryHVAC / Clean Room
readinessGateArea Readiness
activityDescriptionComplete return risers
currentStatusWork In Progress
dashboardBucketIn Progress
priorityCritical
ownerDepartmentVendor
responsiblePersonPradham HVAC
vendorAgencyHVAC Vendor
targetCompletionDate2026-07-31
revisedTargetDate
actualCompletionDate
dependencyPredecessorDucting completion
blockertrue
blockingImpactedItemsClean room air balancing
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaHVAC/clean room verification record and QA/EHS sign-off.
remarksNextAction3 return risers pending, remaining installed
lastUpdatedOn2026-07-17T11:04:15.199+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0.55
criticalBlockerThemeHVAC

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 17, 2026, 11:04 AMUpdated by: SivaSource: Stakeholder update form

Remarks: 3 return risers pending, remaining installed

Old values

current status
Under Discussion
owner department
Engineering / HVAC
responsible person
remarks next action
target completion date

New values

current status
Work In Progress
owner department
Vendor
responsible person
Pradham HVAC
remarks next action
3 return risers pending, remaining installed
target completion date
2026-07-31