PP-0176: Perform air balancing and room pressure differential verification

Task Details

taskIdPP-0176
sourcePlant Head Email / Commissioning Addition
workstreamHVAC / Clean Room
areaClean room
equipmentSystemHVAC System
capacitySize
activityCategoryHVAC / Clean Room
readinessGateArea Readiness
activityDescriptionPerform air balancing and room pressure differential verification
currentStatusNot Started
dashboardBucketNot Started
priorityCritical
ownerDepartmentEngineering
responsiblePersonMr.Sharma Ji / Vendor
vendorAgencyHVAC Vendor
targetCompletionDate2026-09-07
revisedTargetDate
actualCompletionDate
dependencyPredecessorAHU, ducting, HEPA and return riser completion
blockertrue
blockingImpactedItemsClean room qualification
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaHVAC/clean room verification record and QA/EHS sign-off.
remarksNextActionAfter completion of All HVAC installation works
lastUpdatedOn2026-07-17T11:06:57.009+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0
criticalBlockerThemeHVAC

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 17, 2026, 11:06 AMUpdated by: SivaSource: Stakeholder update form

Remarks: After completion of All HVAC installation works

Old values

owner department
Engineering / HVAC
responsible person
remarks next action
target completion date

New values

owner department
Engineering
responsible person
Mr.Sharma Ji / Vendor
remarks next action
After completion of All HVAC installation works
target completion date
2026-09-07