PP-0178: Perform particle count and area classification

Task Details

taskIdPP-0178
sourcePlant Head Email / Commissioning Addition
workstreamHVAC / Clean Room
areaClean room
equipmentSystemHVAC System
capacitySize
activityCategoryHVAC / Clean Room
readinessGateArea Readiness
activityDescriptionPerform particle count and area classification
currentStatusNot Started
dashboardBucketNot Started
priorityCritical
ownerDepartmentEngineering
responsiblePersonMr.Sharma Ji / Vendor
vendorAgencyHVAC Vendor
targetCompletionDate2026-09-07
revisedTargetDate
actualCompletionDate
dependencyPredecessorCleaning, AHU balancing and HEPA integrity
blockertrue
blockingImpactedItemsClean room release
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaHVAC/clean room verification record and QA/EHS sign-off.
remarksNextActionIt will be performed during Clean room area qualification
lastUpdatedOn2026-07-17T11:09:28.683+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0
criticalBlockerThemeHVAC

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 17, 2026, 11:09 AMUpdated by: SivaSource: Stakeholder update form

Remarks: It will be performed during Clean room area qualification

Old values

owner department
Engineering / HVAC
responsible person
remarks next action
target completion date

New values

owner department
Engineering
responsible person
Mr.Sharma Ji / Vendor
remarks next action
It will be performed during Clean room area qualification
target completion date
2026-09-07