Pilot Plant TrackerChecking session…
← Back to Master Task RegisterDashboard

Data source: Supabase

PP-0179: Complete ceiling work after HVAC completion

Task Details

taskIdPP-0179
sourcePlant Head Email / Commissioning Addition
workstreamHVAC / Clean Room
areaClean room
equipmentSystemCeiling System
capacitySize
activityCategoryHVAC / Clean Room
readinessGateArea Readiness
activityDescriptionComplete ceiling work after HVAC completion
currentStatusWork In Progress
dashboardBucketIn Progress
priorityCritical
ownerDepartmentVendor
responsiblePersonPradham
vendorAgencyHVAC Vendor
targetCompletionDate2026-07-31
revisedTargetDate
actualCompletionDate
dependencyPredecessorHVAC ducting and above-ceiling works completion
blockertrue
blockingImpactedItemsClean room readiness
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaHVAC/clean room verification record and QA/EHS sign-off.
remarksNextActionwork under progress
lastUpdatedOn2026-07-14T09:03:09.44+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0.55
criticalBlockerThemeHVAC

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 14, 2026, 9:03 AMUpdated by: SivaSource: Stakeholder update form

Remarks: work under progress, waiting for material

Old values

current status
Not Started
owner department
Engineering / HVAC
responsible person
remarks next action
target completion date

New values

current status
Work In Progress
owner department
Vendor
responsible person
Pradham
remarks next action
work under progress
target completion date
2026-07-31