PP-0180: Perform clean room cleaning and QA/EHS area release

Task Details

taskIdPP-0180
sourcePlant Head Email / Commissioning Addition
workstreamHVAC / Clean Room
areaClean room
equipmentSystemClean Room Area
capacitySize
activityCategoryHVAC / Clean Room
readinessGateArea Readiness
activityDescriptionPerform clean room cleaning and QA/EHS area release
currentStatusWork In Progress
dashboardBucketIn Progress
priorityCritical
ownerDepartmentVendor
responsiblePersonMr.Sharma Ji / Pradham (Vendor)
vendorAgencyHVAC Vendor
targetCompletionDate2026-08-10
revisedTargetDate
actualCompletionDate
dependencyPredecessorCeiling, flooring, HVAC and utilities completion
blockertrue
blockingImpactedItemsClean room operational readiness
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaHVAC/clean room verification record and QA/EHS sign-off.
remarksNextActioncivil, electrical, fabrication works under progress
lastUpdatedOn2026-07-14T08:54:29.502+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0.55
criticalBlockerThemeHVAC

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 14, 2026, 8:54 AMUpdated by: SivaSource: Stakeholder update form

Remarks: civil, electrical, fabrication works under progress

Old values

current status
Not Started
owner department
Engineering / HVAC
responsible person
remarks next action
target completion date

New values

current status
Work In Progress
owner department
Vendor
responsible person
Mr.Sharma Ji / Pradham (Vendor)
remarks next action
civil, electrical, fabrication works under progress
target completion date
2026-08-10