PP-0184: Verify equipment-wise earthing and bonding

Task Details

taskIdPP-0184
sourceCommissioning Expert Addition
workstreamElectrical / Instrumentation
areaPilot plant
equipmentSystemElectrical Distribution
capacitySize
activityCategoryElectrical / Instrumentation
readinessGateElectrical / Instrumentation
activityDescriptionVerify equipment-wise earthing and bonding
currentStatusClosed
dashboardBucketClosed
priorityCritical
ownerDepartmentEngineering
responsiblePersonMr.Sharma Ji
vendorAgencyElectrical Vendor
targetCompletionDate
revisedTargetDate
actualCompletionDate
dependencyPredecessorEquipment installation and electrical panel readiness
blockertrue
blockingImpactedItemsEquipment commissioning and safety clearance
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaSigned E&I checklist, calibration certificate or test record as applicable.
remarksNextActionCompleted, to be verified
lastUpdatedOn2026-07-14T09:52:27.348+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent1
criticalBlockerTheme

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 14, 2026, 9:52 AMUpdated by: SivaSource: Stakeholder update form

Remarks: Completed, to be verified

Old values

current status
Not Started
owner department
Electrical / Instrumentation
responsible person
remarks next action

New values

current status
Closed
owner department
Engineering
responsible person
Mr.Sharma Ji
remarks next action
Completed, to be verified