PP-0189: Complete hydrogenation area utility pipeline work

Task Details

taskIdPP-0189
sourcePlant Head Email / Commissioning Addition
workstreamHydrogenation
areaHydrogenation Area
equipmentSystemHydrogenation Area
capacitySize
activityCategoryPiping / Utility
readinessGateUtility Completion
activityDescriptionComplete hydrogenation area utility pipeline work
currentStatusWork In Progress
dashboardBucketIn Progress
priorityCritical
ownerDepartmentEngineering
responsiblePersonMr.Sharma Ji
vendorAgencyUtility / Piping Vendor
targetCompletionDate2026-08-15
revisedTargetDate
actualCompletionDate
dependencyPredecessor
blockertrue
blockingImpactedItemsUtility availability for hydrogenation trial
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaSigned installation, test, EHS or qualification record as applicable.
remarksNextActionworks under progress
lastUpdatedOn2026-07-16T04:59:22.244+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0.55
criticalBlockerThemeHydrogenation

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 16, 2026, 4:59 AMUpdated by: SivaSource: Stakeholder update form

Remarks: works under progress

Old values

responsible person
remarks next action
Hydrogenation area added as separate high-priority stream due to gas safety requirements.
target completion date

New values

responsible person
Mr.Sharma Ji
remarks next action
works under progress
target completion date
2026-08-15