PP-0190: Complete hydrogenation area civil work

Task Details

taskIdPP-0190
sourcePlant Head Email / Commissioning Addition
workstreamHydrogenation
areaHydrogenation Area
equipmentSystemHydrogenation Area
capacitySize
activityCategoryCivil
readinessGateArea Readiness
activityDescriptionComplete hydrogenation area civil work
currentStatusUnder Discussion
dashboardBucketNot Started
priorityCritical
ownerDepartmentVendor
responsiblePersonSri Ram Enterprises
vendorAgencyCivil Vendor
targetCompletionDate2026-08-31
revisedTargetDate
actualCompletionDate
dependencyPredecessor
blockertrue
blockingImpactedItemsSafe access and area readiness
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaSigned installation, test, EHS or qualification record as applicable.
remarksNextActionOn going
lastUpdatedOn2026-07-17T11:19:53.14+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0.05
criticalBlockerThemeHydrogenation

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 17, 2026, 11:19 AMUpdated by: SivaSource: Stakeholder update form

Remarks: On going

Old values

current status
Work In Progress
owner department
Engineering
responsible person
remarks next action
Hydrogenation area added as separate high-priority stream due to gas safety requirements.
target completion date

New values

current status
Under Discussion
owner department
Vendor
responsible person
Sri Ram Enterprises
remarks next action
On going
target completion date
2026-08-31