PP-0191: Obtain quote for hydrogen manifold

Task Details

taskIdPP-0191
sourcePlant Head Email / Commissioning Addition
workstreamHydrogenation
areaHydrogenation Area
equipmentSystemHydrogen / Nitrogen Manifold
capacitySize
activityCategoryProcurement
readinessGateProcurement
activityDescriptionObtain quote for hydrogen manifold
currentStatusQuote Awaited
dashboardBucketProcurement Pending
priorityCritical
ownerDepartmentPlant Head
responsiblePersonMr.Siva
vendorAgencyGas Manifold Vendor
targetCompletionDate2026-07-20
revisedTargetDate
actualCompletionDate
dependencyPredecessor
blockertrue
blockingImpactedItemsHydrogen reactor commissioning
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaSigned installation, test, EHS or qualification record as applicable.
remarksNextActionQuote received from PCI, awaited for another quote
lastUpdatedOn2026-07-16T04:40:53.398+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0.1
criticalBlockerThemeHydrogenation

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 16, 2026, 4:40 AMUpdated by: SivaSource: Stakeholder update form

Remarks: Quote received from PCI, awaited for another quote

Old values

owner department
Engineering / Procurement
responsible person
remarks next action
Hydrogenation area added as separate high-priority stream due to gas safety requirements.
target completion date

New values

owner department
Plant Head
responsible person
Mr.Siva
remarks next action
Quote received from PCI, awaited for another quote
target completion date
2026-07-20