PP-0193: Issue PO and receive hydrogen / nitrogen manifold materials

Task Details

taskIdPP-0193
sourcePlant Head Email / Commissioning Addition
workstreamHydrogenation
areaHydrogenation Area
equipmentSystemHydrogen / Nitrogen Manifold
capacitySize
activityCategoryProcurement
readinessGateProcurement
activityDescriptionIssue PO and receive hydrogen / nitrogen manifold materials
currentStatusUnder Discussion
dashboardBucketNot Started
priorityCritical
ownerDepartmentPlant Head
responsiblePersonMr.Siva/Mr.Kailas
vendorAgencyGas Manifold Vendor
targetCompletionDate2026-07-24
revisedTargetDate
actualCompletionDate
dependencyPredecessor
blockertrue
blockingImpactedItemsGas manifold installation
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaSigned installation, test, EHS or qualification record as applicable.
remarksNextActionUnder discussions and finalization
lastUpdatedOn2026-07-16T04:48:28.088+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0.05
criticalBlockerThemeHydrogenation

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 16, 2026, 4:48 AMUpdated by: SivaSource: Stakeholder update form

Remarks: Under discussions and finalization

Old values

current status
PO Under Process
owner department
Procurement
responsible person
remarks next action
Hydrogenation area added as separate high-priority stream due to gas safety requirements.
target completion date

New values

current status
Under Discussion
owner department
Plant Head
responsible person
Mr.Siva/Mr.Kailas
remarks next action
Under discussions and finalization
target completion date
2026-07-24