PP-0194: Install hydrogen and nitrogen manifold with tagged valves and regulators

Task Details

taskIdPP-0194
sourcePlant Head Email / Commissioning Addition
workstreamHydrogenation
areaHydrogenation Area
equipmentSystemHydrogen / Nitrogen Manifold
capacitySize
activityCategoryPiping / Gas
readinessGateUtility Completion
activityDescriptionInstall hydrogen and nitrogen manifold with tagged valves and regulators
currentStatusNot Started
dashboardBucketNot Started
priorityCritical
ownerDepartmentVendor
responsiblePersonMr.Sharma Ji / Vendor
vendorAgencyGas Manifold Vendor
targetCompletionDate2026-08-14
revisedTargetDate
actualCompletionDate
dependencyPredecessorHydrogenation utility/civil/gas manifold readiness
blockertrue
blockingImpactedItemsHydrogenation commissioning readiness
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaSigned installation, test, EHS or qualification record as applicable.
remarksNextActiondelivery will takes 2-3 weeks
lastUpdatedOn2026-07-16T04:49:41.104+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0
criticalBlockerThemeHydrogenation

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 16, 2026, 4:49 AMUpdated by: SivaSource: Stakeholder update form

Remarks: delivery will takes 2-3 weeks

Old values

owner department
Engineering
responsible person
remarks next action
Hydrogenation area added as separate high-priority stream due to gas safety requirements.
target completion date

New values

owner department
Vendor
responsible person
Mr.Sharma Ji / Vendor
remarks next action
delivery will takes 2-3 weeks
target completion date
2026-08-14