Pilot Plant TrackerChecking session…
← Back to Master Task RegisterDashboard

Data source: Supabase

PP-0195: Perform pressure test, leak test and purge verification for gas manifold

Task Details

taskIdPP-0195
sourcePlant Head Email / Commissioning Addition
workstreamHydrogenation
areaHydrogenation Area
equipmentSystemHydrogen / Nitrogen Manifold
capacitySize
activityCategoryTesting
readinessGateSafety Readiness
activityDescriptionPerform pressure test, leak test and purge verification for gas manifold
currentStatusNot Started
dashboardBucketNot Started
priorityCritical
ownerDepartmentProduction
responsiblePersonMr.Sharma Ji / Mr.Jain Ji
vendorAgencyGas Manifold Vendor
targetCompletionDate2026-08-20
revisedTargetDate
actualCompletionDate
dependencyPredecessorHydrogenation utility/civil/gas manifold readiness
blockertrue
blockingImpactedItemsHydrogenation safety clearance
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaSigned installation, test, EHS or qualification record as applicable.
remarksNextActionTesting can be performed after completion of installation
lastUpdatedOn2026-07-16T04:50:48.037+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0
criticalBlockerThemeHydrogenation

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 16, 2026, 4:50 AMUpdated by: SivaSource: Stakeholder update form

Remarks: Testing can be performed after completion of installation

Old values

owner department
Engineering / EHS
responsible person
remarks next action
Hydrogenation area added as separate high-priority stream due to gas safety requirements.
target completion date

New values

owner department
Production
responsible person
Mr.Sharma Ji / Mr.Jain Ji
remarks next action
Testing can be performed after completion of installation
target completion date
2026-08-20