PP-0198: Prepare purging, inerting and emergency response SOPs

Task Details

taskIdPP-0198
sourcePlant Head Email / Commissioning Addition
workstreamHydrogenation
areaHydrogenation Area
equipmentSystemHydrogenation Area
capacitySize
activityCategoryDocumentation
readinessGateDocumentation
activityDescriptionPrepare purging, inerting and emergency response SOPs
currentStatusNot Started
dashboardBucketNot Started
priorityCritical
ownerDepartmentProduction
responsiblePersonMr.Nikhil sir / Mr.Jain / Mr.Bagal
vendorAgency
targetCompletionDate2026-09-15
revisedTargetDate
actualCompletionDate
dependencyPredecessorHydrogenation utility/civil/gas manifold readiness
blockerfalse
blockingImpactedItemsHydrogenation operation readiness
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaSigned installation, test, EHS or qualification record as applicable.
remarksNextActionAfter completion of all Hydrogenation works
lastUpdatedOn2026-07-17T11:29:47.914+00:00
updatedBySiva
daysToTarget
scheduleFlagNo Target
completionPercent0
criticalBlockerThemeHydrogenation

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 17, 2026, 11:29 AMUpdated by: SivaSource: Stakeholder update form

Remarks: After completion of all Hydrogenation works

Old values

owner department
Production / EHS / QA
responsible person
remarks next action
Hydrogenation area added as separate high-priority stream due to gas safety requirements.
target completion date

New values

owner department
Production
responsible person
Mr.Nikhil sir / Mr.Jain / Mr.Bagal
remarks next action
After completion of all Hydrogenation works
target completion date
2026-09-15