PP-0200: Execute hydrogen reactor commissioning trial

Task Details

taskIdPP-0200
sourcePlant Head Email / Commissioning Addition
workstreamHydrogenation
areaHydrogenation Area
equipmentSystemHydrogen Reactor 250 L
capacitySize250 L
activityCategoryCommissioning
readinessGateCommissioning
activityDescriptionExecute hydrogen reactor commissioning trial
currentStatusNot Started
dashboardBucketNot Started
priorityCritical
ownerDepartmentVendor
responsiblePersonAmir Tanks
vendorAgencyHydrogen Reactor Vendor
targetCompletionDate2026-08-10
revisedTargetDate
actualCompletionDate
dependencyPredecessorHydrogenation utility/civil/gas manifold readiness
blockertrue
blockingImpactedItemsHydrogenation qualification readiness
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaSigned installation, test, EHS or qualification record as applicable.
remarksNextActionAfter completion of other activities
lastUpdatedOn2026-07-16T04:55:19.31+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0
criticalBlockerThemeHydrogenation

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 16, 2026, 4:55 AMUpdated by: SivaSource: Stakeholder update form

Remarks: After completion of other activities

Old values

owner department
Engineering / Production / EHS
responsible person
remarks next action
Hydrogenation area added as separate high-priority stream due to gas safety requirements.
target completion date

New values

owner department
Vendor
responsible person
Amir Tanks
remarks next action
After completion of other activities
target completion date
2026-08-10