PP-0201: Prepare and execute IQ/OQ package for hydrogen reactor

Task Details

taskIdPP-0201
sourcePlant Head Email / Commissioning Addition
workstreamHydrogenation
areaHydrogenation Area
equipmentSystemHydrogen Reactor 250 L
capacitySize250 L
activityCategoryQualification
readinessGateQualification
activityDescriptionPrepare and execute IQ/OQ package for hydrogen reactor
currentStatusNot Started
dashboardBucketNot Started
priorityCritical
ownerDepartmentQA / Validation
responsiblePerson
vendorAgency
targetCompletionDate
revisedTargetDate
actualCompletionDate
dependencyPredecessorHydrogenation utility/civil/gas manifold readiness
blockerfalse
blockingImpactedItemsReady-to-operate approval
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaSigned installation, test, EHS or qualification record as applicable.
remarksNextActionHydrogenation area added as separate high-priority stream due to gas safety requirements.
lastUpdatedOn
updatedBy
daysToTarget
scheduleFlagNo Target
completionPercent0
criticalBlockerThemeHydrogenation

Stakeholder Task Update

Updates require DATA_SOURCE=supabase. CSV mode remains read-only.

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Update history is available when DATA_SOURCE=supabase is enabled. CSV mode remains read-only.