PP-0210: Complete calibration certificates for critical instruments

Task Details

taskIdPP-0210
sourceCommissioning Expert Addition
workstreamQualification
areaPilot plant
equipmentSystemCalibration Pack
capacitySize
activityCategoryCalibration
readinessGateQualification
activityDescriptionComplete calibration certificates for critical instruments
currentStatusNot Started
dashboardBucketNot Started
priorityHigh
ownerDepartmentEngineering
responsiblePersonMr.Sharma Ji/ Mr.Bhishama Ji
vendorAgency
targetCompletionDate2026-08-10
revisedTargetDate
actualCompletionDate
dependencyPredecessorInstrument installation completion
blockerfalse
blockingImpactedItemsFinal qualification and ready-to-operate status
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaApproved document/training/clearance/handover record.
remarksNextActionEngineering / QA work together
lastUpdatedOn2026-07-14T09:01:28.293+00:00
updatedBySiva
daysToTarget
scheduleFlagNo Target
completionPercent0
criticalBlockerTheme

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 14, 2026, 9:01 AMUpdated by: SivaSource: Stakeholder update form

Remarks: Engineering / QA work together

Old values

owner department
QA / Validation / E&I
responsible person
remarks next action
target completion date

New values

owner department
Engineering
responsible person
Mr.Sharma Ji/ Mr.Bhishama Ji
remarks next action
Engineering / QA work together
target completion date
2026-08-10