Remarks: After completion of work, to be started during qualification
Old values
- responsible person
- —
New values
- responsible person
- Mr.Sharma
Data source: Supabase
| taskId | PP-0215 |
|---|---|
| source | Commissioning Expert Addition |
| workstream | Qualification |
| area | Pilot plant |
| equipmentSystem | PM Plan |
| capacitySize | |
| activityCategory | Documentation |
| readinessGate | Operational Handover |
| activityDescription | Create preventive maintenance plan and lubrication checklist |
| currentStatus | Not Started |
| dashboardBucket | Not Started |
| priority | High |
| ownerDepartment | Engineering |
| responsiblePerson | Mr.Sharma |
| vendorAgency | |
| targetCompletionDate | |
| revisedTargetDate | |
| actualCompletionDate | |
| dependencyPredecessor | Vendor manuals and maintenance recommendations |
| blocker | false |
| blockingImpactedItems | Final qualification and ready-to-operate status |
| commissioningImpact | false |
| qualificationImpact | true |
| evidenceAcceptanceCriteria | Approved document/training/clearance/handover record. |
| remarksNextAction | |
| lastUpdatedOn | 2026-07-27T08:45:55.097+00:00 |
| updatedBy | Siva |
| daysToTarget | |
| scheduleFlag | No Target |
| completionPercent | 0 |
| criticalBlockerTheme | Scrubber |
No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.
Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.
No upstream task dependencies are mapped for this task.
No downstream task dependencies are mapped for this task.
Remarks: After completion of work, to be started during qualification