PP-0215: Create preventive maintenance plan and lubrication checklist

Task Details

taskIdPP-0215
sourceCommissioning Expert Addition
workstreamQualification
areaPilot plant
equipmentSystemPM Plan
capacitySize
activityCategoryDocumentation
readinessGateOperational Handover
activityDescriptionCreate preventive maintenance plan and lubrication checklist
currentStatusNot Started
dashboardBucketNot Started
priorityHigh
ownerDepartmentEngineering
responsiblePersonMr.Sharma
vendorAgency
targetCompletionDate
revisedTargetDate
actualCompletionDate
dependencyPredecessorVendor manuals and maintenance recommendations
blockerfalse
blockingImpactedItemsFinal qualification and ready-to-operate status
commissioningImpactfalse
qualificationImpacttrue
evidenceAcceptanceCriteriaApproved document/training/clearance/handover record.
remarksNextAction
lastUpdatedOn2026-07-27T08:45:55.097+00:00
updatedBySiva
daysToTarget
scheduleFlagNo Target
completionPercent0
criticalBlockerThemeScrubber

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 27, 2026, 8:45 AMUpdated by: SivaSource: Stakeholder update form

Remarks: After completion of work, to be started during qualification

Old values

responsible person

New values

responsible person
Mr.Sharma