PP-0216: Complete operator and maintenance team training

Task Details

taskIdPP-0216
sourceCommissioning Expert Addition
workstreamQualification
areaPilot plant
equipmentSystemOperator Training
capacitySize
activityCategoryTraining
readinessGateOperational Handover
activityDescriptionComplete operator and maintenance team training
currentStatusNot Started
dashboardBucketNot Started
priorityHigh
ownerDepartmentProduction / Engineering / QA
responsiblePersonMr.Jain / Mr.Bagal
vendorAgency
targetCompletionDate
revisedTargetDate
actualCompletionDate
dependencyPredecessorApproved SOPs and equipment commissioning
blockerfalse
blockingImpactedItemsFinal qualification and ready-to-operate status
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaApproved document/training/clearance/handover record.
remarksNextAction
lastUpdatedOn2026-07-31T08:58:42.268+00:00
updatedBySiva
daysToTarget
scheduleFlagNo Target
completionPercent0
criticalBlockerTheme

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 31, 2026, 8:58 AMUpdated by: SivaSource: Stakeholder update form

Remarks: to be done

Old values

responsible person

New values

responsible person
Mr.Jain / Mr.Bagal