PP-0219: Release PO and mobilize insulation vendor for chilled/brine/hot water/steam insulation
Task Details
| taskId | PP-0219 |
|---|---|
| source | Sheet1 priority |
| workstream | Procurement / Vendor |
| area | Pilot plant |
| equipmentSystem | Insulation Package |
| capacitySize | |
| activityCategory | Procurement |
| readinessGate | Procurement |
| activityDescription | Release PO and mobilize insulation vendor for chilled/brine/hot water/steam insulation |
| currentStatus | PO Under Process |
| dashboardBucket | Procurement Pending |
| priority | Critical |
| ownerDepartment | Procurement / Engineering |
| responsiblePerson | |
| vendorAgency | Insulation Vendor |
| targetCompletionDate | |
| revisedTargetDate | |
| actualCompletionDate | |
| dependencyPredecessor | Commercial approval and finalized scope |
| blocker | true |
| blockingImpactedItems | Chilled water/brine commissioning, GLR condenser installation, hot water/steam readiness |
| commissioningImpact | true |
| qualificationImpact | true |
| evidenceAcceptanceCriteria | PO released, vendor mobilized, insulation completed and inspected. |
| remarksNextAction | Explicit critical-path item from priority sheet. |
| lastUpdatedOn | |
| updatedBy | |
| daysToTarget | |
| scheduleFlag | Blocked |
| completionPercent | 0.2 |
| criticalBlockerTheme | Insulation |
Stakeholder Task Update
No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.
Blocked By / Upstream Tasks
Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.
No upstream task dependencies are mapped for this task.
Blocking / Downstream Tasks
No downstream task dependencies are mapped for this task.
Recent Update History
No update history has been recorded for this task yet.