PP-0219: Release PO and mobilize insulation vendor for chilled/brine/hot water/steam insulation

Task Details

taskIdPP-0219
sourceSheet1 priority
workstreamProcurement / Vendor
areaPilot plant
equipmentSystemInsulation Package
capacitySize
activityCategoryProcurement
readinessGateProcurement
activityDescriptionRelease PO and mobilize insulation vendor for chilled/brine/hot water/steam insulation
currentStatusPO Under Process
dashboardBucketProcurement Pending
priorityCritical
ownerDepartmentProcurement / Engineering
responsiblePerson
vendorAgencyInsulation Vendor
targetCompletionDate
revisedTargetDate
actualCompletionDate
dependencyPredecessorCommercial approval and finalized scope
blockertrue
blockingImpactedItemsChilled water/brine commissioning, GLR condenser installation, hot water/steam readiness
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaPO released, vendor mobilized, insulation completed and inspected.
remarksNextActionExplicit critical-path item from priority sheet.
lastUpdatedOn
updatedBy
daysToTarget
scheduleFlagBlocked
completionPercent0.2
criticalBlockerThemeInsulation

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

No update history has been recorded for this task yet.