PP-0219: Release PO and mobilize insulation vendor for chilled/brine/hot water/steam insulation

Task Details

taskIdPP-0219
sourceSheet1 priority
workstreamProcurement / Vendor
areaPilot plant
equipmentSystemInsulation Package
capacitySize
activityCategoryProcurement
readinessGateProcurement
activityDescriptionRelease PO and mobilize insulation vendor for chilled/brine/hot water/steam insulation
currentStatusWork In Progress
dashboardBucketIn Progress
priorityCritical
ownerDepartmentVendor
responsiblePersonMr.Sharma Ji / Ravi Insulation
vendorAgencyInsulation Vendor
targetCompletionDate2026-07-31
revisedTargetDate
actualCompletionDate
dependencyPredecessorCommercial approval and finalized scope
blockertrue
blockingImpactedItemsChilled water/brine commissioning, GLR condenser installation, hot water/steam readiness
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaPO released, vendor mobilized, insulation completed and inspected.
remarksNextActionwork under progress
lastUpdatedOn2026-07-17T11:39:31.312+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0.55
criticalBlockerThemeInsulation

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 17, 2026, 11:39 AMUpdated by: SivaSource: Stakeholder update form

Remarks: work under progress

Old values

current status
PO Under Process
owner department
Procurement / Engineering
responsible person
remarks next action
Explicit critical-path item from priority sheet.
target completion date

New values

current status
Work In Progress
owner department
Vendor
responsible person
Mr.Sharma Ji / Ravi Insulation
remarks next action
work under progress
target completion date
2026-07-31