PP-0224: Complete electrical connection, earthing and safety interlock check for Centrifuge 1

Task Details

taskIdPP-0224
sourceCommissioning Expert Addition
workstreamElectrical / Instrumentation
areaIntermediate / Clean room
equipmentSystemCentrifuge 1
capacitySize
activityCategoryElectrical / Instrumentation
readinessGateElectrical / Instrumentation
activityDescriptionComplete electrical connection, earthing and safety interlock check for Centrifuge 1
currentStatusWork In Progress
dashboardBucketIn Progress
priorityCritical
ownerDepartmentElectrical / Instrumentation
responsiblePersonMr.Sharma
vendorAgencyE&I Vendor
targetCompletionDate2026-08-14
revisedTargetDate
actualCompletionDate
dependencyPredecessorCentrifuge 1 installation completion
blockertrue
blockingImpactedItemsCentrifuge 1 trial run
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaE&I checklist and interlock verification completed.
remarksNextActionwork under progress
lastUpdatedOn2026-07-28T07:33:56.506+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0.55
criticalBlockerTheme

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 28, 2026, 7:33 AMUpdated by: SivaSource: Stakeholder update form

Remarks: work under progress

Old values

current status
Not Started
responsible person
Mr.Sharma Ji
remarks next action
To be started after placing centrifuge
target completion date
2026-07-21

New values

current status
Work In Progress
responsible person
Mr.Sharma
remarks next action
work under progress
target completion date
2026-08-14
Jul 14, 2026, 9:14 AMUpdated by: SivaSource: Stakeholder update form

Remarks: To be started after placing centrifuge

Old values

responsible person
remarks next action
target completion date

New values

responsible person
Mr.Sharma Ji
remarks next action
To be started after placing centrifuge
target completion date
2026-07-21