Remarks: Ml's tank to be finalized
Old values
- responsible person
- —
- target completion date
- —
New values
- responsible person
- Mr.Sharma Ji / Mr.Jain Ji
- target completion date
- 2026-07-31
Data source: Supabase
| taskId | PP-0225 |
|---|---|
| source | Commissioning Expert Addition |
| workstream | Equipment |
| area | Intermediate / Clean room |
| equipmentSystem | Centrifuge 1 |
| capacitySize | |
| activityCategory | Commissioning |
| readinessGate | Commissioning |
| activityDescription | Execute no-load trial and functional checks for Centrifuge 1 |
| currentStatus | Not Started |
| dashboardBucket | Not Started |
| priority | High |
| ownerDepartment | Engineering / Production |
| responsiblePerson | Mr.Sharma Ji / Mr.Jain Ji |
| vendorAgency | Centrifuge Vendor |
| targetCompletionDate | 2026-07-31 |
| revisedTargetDate | |
| actualCompletionDate | |
| dependencyPredecessor | Centrifuge 1 installation and E&I readiness |
| blocker | false |
| blockingImpactedItems | |
| commissioningImpact | true |
| qualificationImpact | true |
| evidenceAcceptanceCriteria | Trial run report and functional checklist. |
| remarksNextAction | |
| lastUpdatedOn | 2026-07-14T09:20:37.51+00:00 |
| updatedBy | Siva |
| daysToTarget | |
| scheduleFlag | No Target |
| completionPercent | 0 |
| criticalBlockerTheme |
No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.
Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.
No upstream task dependencies are mapped for this task.
No downstream task dependencies are mapped for this task.
Remarks: Ml's tank to be finalized