PP-0228: Install Centrifuge 2 in final location

Task Details

taskIdPP-0228
sourcePlant Head Email / Sheet1 priority
workstreamEquipment
areaIntermediate / Clean room
equipmentSystemCentrifuge 2
capacitySize
activityCategoryInstallation
readinessGateMechanical Completion
activityDescriptionInstall Centrifuge 2 in final location
currentStatusClosed
dashboardBucketClosed
priorityCritical
ownerDepartmentEngineering
responsiblePersonMr.Sharma Ji
vendorAgencyCentrifuge Vendor
targetCompletionDate2026-07-17
revisedTargetDate
actualCompletionDate
dependencyPredecessorArea readiness, foundation/baseframe and vendor availability
blockertrue
blockingImpactedItemsCentrifuge 2 commissioning
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaEquipment installed, leveled, anchored and tagged.
remarksNextActionPlaced in final location
lastUpdatedOn2026-07-17T08:52:09.357+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent1
criticalBlockerTheme

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 17, 2026, 8:52 AMUpdated by: SivaSource: Stakeholder update form

Remarks: Placed in final location

Old values

current status
Not Started
responsible person
remarks next action
target completion date

New values

current status
Closed
responsible person
Mr.Sharma Ji
remarks next action
Placed in final location
target completion date
2026-07-17