PP-0233: Install Sifter in final location

Task Details

taskIdPP-0233
sourcePlant Head Email / Sheet1 priority
workstreamEquipment
areaIntermediate
equipmentSystemSifter
capacitySize
activityCategoryInstallation
readinessGateMechanical Completion
activityDescriptionInstall Sifter in final location
currentStatusWork In Progress
dashboardBucketIn Progress
priorityCritical
ownerDepartmentEngineering
responsiblePersonMr.Sharma
vendorAgencySifter Vendor
targetCompletionDate2026-08-14
revisedTargetDate
actualCompletionDate
dependencyPredecessorArea readiness, foundation/baseframe and vendor availability
blockertrue
blockingImpactedItemsSifter commissioning
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaEquipment installed, leveled, anchored and tagged.
remarksNextAction
lastUpdatedOn2026-07-27T11:20:18.829+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0.55
criticalBlockerTheme

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 27, 2026, 11:20 AMUpdated by: SivaSource: Stakeholder update form

Remarks: Sifter installation completed in PP Area

Old values

current status
Not Started

New values

current status
Work In Progress
Jul 27, 2026, 11:19 AMUpdated by: SivaSource: Stakeholder update form

Remarks: PP Area Sifter installation completed

Old values

responsible person
target completion date

New values

responsible person
Mr.Sharma
target completion date
2026-08-14