PP-0239: Complete electrical connection, earthing and safety interlock check for Multi-mill

Task Details

taskIdPP-0239
sourceCommissioning Expert Addition
workstreamElectrical / Instrumentation
areaIntermediate
equipmentSystemMulti-mill
capacitySize
activityCategoryElectrical / Instrumentation
readinessGateElectrical / Instrumentation
activityDescriptionComplete electrical connection, earthing and safety interlock check for Multi-mill
currentStatusNot Started
dashboardBucketNot Started
priorityCritical
ownerDepartmentElectrical / Instrumentation
responsiblePersonMr.Sharma Ji / Mr.Jain Ji
vendorAgencyE&I Vendor
targetCompletionDate2026-08-14
revisedTargetDate
actualCompletionDate
dependencyPredecessorMulti-mill installation completion
blockertrue
blockingImpactedItemsMulti-mill trial run
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaE&I checklist and interlock verification completed.
remarksNextActionReceived, to be installed. Electrical connection work completed
lastUpdatedOn2026-07-23T04:51:33.158+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0
criticalBlockerTheme

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 23, 2026, 4:51 AMUpdated by: SivaSource: Stakeholder update form

Remarks: Received, to be installed. Electrical connection work completed

Old values

responsible person
remarks next action
target completion date

New values

responsible person
Mr.Sharma Ji / Mr.Jain Ji
remarks next action
Received, to be installed. Electrical connection work completed
target completion date
2026-08-14