PP-0240: Execute no-load trial and functional checks for Multi-mill

Task Details

taskIdPP-0240
sourceCommissioning Expert Addition
workstreamEquipment
areaIntermediate
equipmentSystemMulti-mill
capacitySize
activityCategoryCommissioning
readinessGateCommissioning
activityDescriptionExecute no-load trial and functional checks for Multi-mill
currentStatusNot Started
dashboardBucketNot Started
priorityHigh
ownerDepartmentEngineering / Production
responsiblePersonMr.Sharma / Mr.Jain
vendorAgencyMulti-mill Vendor
targetCompletionDate2026-08-14
revisedTargetDate
actualCompletionDate
dependencyPredecessorMulti-mill installation and E&I readiness
blockerfalse
blockingImpactedItems
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaTrial run report and functional checklist.
remarksNextActionReceived, to be installed. Electrical connection work completed
lastUpdatedOn2026-07-23T04:52:32.265+00:00
updatedBySiva
daysToTarget
scheduleFlagNo Target
completionPercent0
criticalBlockerTheme

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 23, 2026, 4:52 AMUpdated by: SivaSource: Stakeholder update form

Remarks: Received, to be installed. Electrical connection work completed

Old values

responsible person
remarks next action
target completion date

New values

responsible person
Mr.Sharma / Mr.Jain
remarks next action
Received, to be installed. Electrical connection work completed
target completion date
2026-08-14