PP-0241: Prepare and execute IQ/OQ package for Multi-mill

Task Details

taskIdPP-0241
sourceCommissioning Expert Addition
workstreamQualification
areaIntermediate
equipmentSystemMulti-mill
capacitySize
activityCategoryQualification
readinessGateQualification
activityDescriptionPrepare and execute IQ/OQ package for Multi-mill
currentStatusNot Started
dashboardBucketNot Started
priorityHigh
ownerDepartmentQA / Validation
responsiblePersonMr.Sharma / Mr.Jain
vendorAgency
targetCompletionDate2026-09-15
revisedTargetDate
actualCompletionDate
dependencyPredecessorMulti-mill commissioning and documentation closure
blockerfalse
blockingImpactedItems
commissioningImpactfalse
qualificationImpacttrue
evidenceAcceptanceCriteriaApproved IQ/OQ report and QA release.
remarksNextActionQualification to be started after installation
lastUpdatedOn2026-07-23T04:53:40.022+00:00
updatedBySiva
daysToTarget
scheduleFlagNo Target
completionPercent0
criticalBlockerTheme

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 23, 2026, 4:53 AMUpdated by: SivaSource: Stakeholder update form

Remarks: Qualification to be started after installation

Old values

responsible person
remarks next action
target completion date

New values

responsible person
Mr.Sharma / Mr.Jain
remarks next action
Qualification to be started after installation
target completion date
2026-09-15