Showing Equipment: SSR-204 — 9 of 241 tasks
| Task | Workstream | Area | Equipment | Description | Status | Priority | Owner | Target | Manual Blocker | Dependency Blocked | Blocked By | Blocking | C Impact | Q Impact |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| PP-0028 | Equipment | Intermediate | SSR-204 | Receive and install stainless steel reactor in final position | Closed | High | Engineering Unassigned | No Target | No | No | 0 | 0 | No | No |
| PP-0029 | Documentation | Intermediate | SSR-204 | Receive approved reactor drawings from Amir Tanks | Material Awaited | High | Engineering Unassigned | No Target | Yes | No | 0 | 0 | No | Yes |
| PP-0030 | Equipment | Intermediate | SSR-204 | Fix and verify reactor bottom valve | Not Started | Critical | Engineering Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0031 | Utility | Intermediate | SSR-204 | Complete vacuum connection to reactor | PO Under Process | Critical | Engineering / Procurement Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0032 | Safety / EHS | Intermediate | SSR-204 | Complete scrubber / vent connection to reactor | PO Under Process | Critical | Engineering / Procurement Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0033 | Utility | Intermediate | SSR-204 | Complete hot water connection to reactor jacket / coil | Not Started | Critical | Engineering Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0034 | Equipment | Intermediate | SSR-204 | Complete reflux lines and interconnecting piping | Work In Progress | Critical | Engineering Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0035 | Equipment | Intermediate | SSR-204 | Execute equipment installation checklist and no-load commissioning trial | Not Started | Critical | Engineering / Production Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0036 | Qualification | Intermediate | SSR-204 | Prepare and execute IQ/OQ package for reactor | Not Started | High | QA / Validation Unassigned | No Target | No | No | 0 | 0 | No | Yes |
Imported columns supported: 31. Closed and qualified tasks remain visible unless an open-only filter is selected.