PP-0003: Fix and verify reactor bottom valve
Task Details
| taskId | PP-0003 |
|---|---|
| source | Sheet2 transformed |
| workstream | Equipment |
| area | Intermediate |
| equipmentSystem | SSR-201 |
| capacitySize | 130 |
| activityCategory | Mechanical |
| readinessGate | Mechanical Completion |
| activityDescription | Fix and verify reactor bottom valve |
| currentStatus | Not Started |
| dashboardBucket | Not Started |
| priority | Critical |
| ownerDepartment | Engineering |
| responsiblePerson | |
| vendorAgency | Amir Tanks |
| targetCompletionDate | |
| revisedTargetDate | |
| actualCompletionDate | |
| dependencyPredecessor | Bottom valve and vendor availability |
| blocker | true |
| blockingImpactedItems | SSR-201 mechanical completion and trial operation |
| commissioningImpact | true |
| qualificationImpact | true |
| evidenceAcceptanceCriteria | Bottom valve installed, leak-tight, accessible, and tagged. |
| remarksNextAction | |
| lastUpdatedOn | |
| updatedBy | |
| daysToTarget | |
| scheduleFlag | Blocked |
| completionPercent | 0 |
| criticalBlockerTheme |
Stakeholder Task Update
Updates require DATA_SOURCE=supabase. CSV mode remains read-only.
No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.
Blocked By / Upstream Tasks
Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.
| Task | Description | Status | Owner | Dependency | Blocking? |
|---|---|---|---|---|---|
| PP-0002 | Receive approved reactor drawings from Amir Tanks | Material Awaited | Engineering Unassigned | prerequisite: Approved vendor drawings support SSR-201 bottom valve installation verification. | Blocking |
Blocking / Downstream Tasks
| Task | Description | Status | Owner | Dependency | Current Effect |
|---|---|---|---|---|---|
| PP-0008 | Execute equipment installation checklist and no-load commissioning trial | Not Started | Engineering / Production Unassigned | blocks: SSR-201 bottom valve must be fixed before SSR-201 no-load commissioning. | Blocking successor |
Recent Update History
Update history is available when DATA_SOURCE=supabase is enabled. CSV mode remains read-only.