Pilot Plant TrackerChecking session…
← Back to Master Task RegisterDashboard

Data source: Supabase

PP-0003: Fix and verify reactor bottom valve

Task Details

taskIdPP-0003
sourceSheet2 transformed
workstreamEquipment
areaIntermediate
equipmentSystemSSR-201
capacitySize130
activityCategoryMechanical
readinessGateMechanical Completion
activityDescriptionFix and verify reactor bottom valve
currentStatusPO Under Process
dashboardBucketProcurement Pending
priorityCritical
ownerDepartmentProcurement
responsiblePersonMr.Kailas
vendorAgencyAmir Tanks
targetCompletionDate2026-07-16
revisedTargetDate
actualCompletionDate
dependencyPredecessorBottom valve and vendor availability
blockerfalse
blockingImpactedItemsSSR-201 mechanical completion and trial operation
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaBottom valve installed, leak-tight, accessible, and tagged.
remarksNextActionCan be completed before equipment qualification
lastUpdatedOn2026-07-14T05:07:59.944+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0.2
criticalBlockerTheme

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

TaskDescriptionStatusOwnerDependencyBlocking?
PP-0002Receive approved reactor drawings from Amir TanksMaterial AwaitedEngineering
Mr.Sharma Ji
prerequisite: Approved vendor drawings support SSR-201 bottom valve installation verification.Blocking

Blocking / Downstream Tasks

TaskDescriptionStatusOwnerDependencyCurrent Effect
PP-0008Execute equipment installation checklist and no-load commissioning trialNot StartedVendor
Amir Tanks
blocks: SSR-201 bottom valve must be fixed before SSR-201 no-load commissioning.Blocking successor

Recent Update History

Jul 14, 2026, 5:07 AMUpdated by: SivaSource: Stakeholder update form

Remarks: Can be completed before equipment qualification

Old values

blocker
Yes
current status
Not Started
owner department
Engineering
responsible person
remarks next action
target completion date

New values

blocker
No
current status
PO Under Process
owner department
Procurement
responsible person
Mr.Kailas
remarks next action
Can be completed before equipment qualification
target completion date
2026-07-16