Remarks: completed
Old values
- current status
- PO Under Process
- responsible person
- Mr.Kailas
New values
- current status
- Closed
- responsible person
- Mr.Kailas / Mr.Sharma
Data source: Supabase
| taskId | PP-0003 |
|---|---|
| source | Sheet2 transformed |
| workstream | Equipment |
| area | Intermediate |
| equipmentSystem | SSR-201 |
| capacitySize | 130 |
| activityCategory | Mechanical |
| readinessGate | Mechanical Completion |
| activityDescription | Fix and verify reactor bottom valve |
| currentStatus | Closed |
| dashboardBucket | Closed |
| priority | Critical |
| ownerDepartment | Procurement |
| responsiblePerson | Mr.Kailas / Mr.Sharma |
| vendorAgency | Amir Tanks |
| targetCompletionDate | 2026-07-16 |
| revisedTargetDate | |
| actualCompletionDate | |
| dependencyPredecessor | Bottom valve and vendor availability |
| blocker | false |
| blockingImpactedItems | SSR-201 mechanical completion and trial operation |
| commissioningImpact | true |
| qualificationImpact | true |
| evidenceAcceptanceCriteria | Bottom valve installed, leak-tight, accessible, and tagged. |
| remarksNextAction | Can be completed before equipment qualification |
| lastUpdatedOn | 2026-07-29T08:53:44.737+00:00 |
| updatedBy | Siva |
| daysToTarget | |
| scheduleFlag | Blocked |
| completionPercent | 1 |
| criticalBlockerTheme |
No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.
Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.
| Task | Description | Status | Owner | Dependency | Blocking? |
|---|---|---|---|---|---|
| PP-0002 | Receive approved reactor drawings from Amir Tanks | Material Awaited | Engineering Dharmendra Sharma | prerequisite: Approved vendor drawings support SSR-201 bottom valve installation verification. | Blocking |
| Task | Description | Status | Owner | Dependency | Current Effect |
|---|---|---|---|---|---|
| PP-0008 | Execute equipment installation checklist and no-load commissioning trial | Not Started | Vendor Amir Tanks | blocks: SSR-201 bottom valve must be fixed before SSR-201 no-load commissioning. | Predecessor cleared |
Remarks: completed
Remarks: Can be completed before equipment qualification