PP-0008: Execute equipment installation checklist and no-load commissioning trial
Task Details
| taskId | PP-0008 |
|---|---|
| source | Commissioning Expert Addition |
| workstream | Equipment |
| area | Intermediate |
| equipmentSystem | SSR-201 |
| capacitySize | 130 |
| activityCategory | Commissioning |
| readinessGate | Commissioning |
| activityDescription | Execute equipment installation checklist and no-load commissioning trial |
| currentStatus | Not Started |
| dashboardBucket | Not Started |
| priority | Critical |
| ownerDepartment | Engineering / Production |
| responsiblePerson | |
| vendorAgency | Amir Tanks |
| targetCompletionDate | |
| revisedTargetDate | |
| actualCompletionDate | |
| dependencyPredecessor | Mechanical, utility, electrical, scrubber and vacuum readiness |
| blocker | true |
| blockingImpactedItems | SSR-201 qualification readiness |
| commissioningImpact | true |
| qualificationImpact | true |
| evidenceAcceptanceCriteria | Signed commissioning checklist and trial run report. |
| remarksNextAction | |
| lastUpdatedOn | |
| updatedBy | |
| daysToTarget | |
| scheduleFlag | Blocked |
| completionPercent | 0 |
| criticalBlockerTheme | Vacuum |
Stakeholder Task Update
Updates require DATA_SOURCE=supabase. CSV mode remains read-only.
No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.
Blocked By / Upstream Tasks
Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.
| Task | Description | Status | Owner | Dependency | Blocking? |
|---|---|---|---|---|---|
| PP-0003 | Fix and verify reactor bottom valve | Not Started | Engineering Unassigned | blocks: SSR-201 bottom valve must be fixed before SSR-201 no-load commissioning. | Blocking |
| PP-0004 | Complete vacuum connection to reactor | PO Under Process | Engineering / Procurement Unassigned | blocks: SSR-201 vacuum connection must be complete before SSR-201 no-load commissioning. | Blocking |
| PP-0005 | Complete scrubber / vent connection to reactor | PO Under Process | Engineering / Procurement Unassigned | blocks: SSR-201 scrubber/vent connection must be complete before SSR-201 no-load commissioning. | Blocking |
| PP-0006 | Complete hot water connection to reactor jacket / coil | Not Started | Engineering Unassigned | blocks: SSR-201 hot water connection must be complete before SSR-201 no-load commissioning. | Blocking |
Blocking / Downstream Tasks
| Task | Description | Status | Owner | Dependency | Current Effect |
|---|---|---|---|---|---|
| PP-0009 | Prepare and execute IQ/OQ package for reactor | Not Started | QA / Validation Unassigned | prerequisite: SSR-201 commissioning records are required before IQ/OQ execution. | Blocking successor |