PP-0008: Execute equipment installation checklist and no-load commissioning trial

Task Details

taskIdPP-0008
sourceCommissioning Expert Addition
workstreamEquipment
areaIntermediate
equipmentSystemSSR-201
capacitySize130
activityCategoryCommissioning
readinessGateCommissioning
activityDescriptionExecute equipment installation checklist and no-load commissioning trial
currentStatusNot Started
dashboardBucketNot Started
priorityCritical
ownerDepartmentVendor
responsiblePersonAmir Tanks
vendorAgencyAmir Tanks
targetCompletionDate2026-07-15
revisedTargetDate2026-07-30
actualCompletionDate
dependencyPredecessorMechanical, utility, electrical, scrubber and vacuum readiness
blockertrue
blockingImpactedItemsSSR-201 qualification readiness
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaSigned commissioning checklist and trial run report.
remarksNextActionwaiting for Amir tanks Team, awaiting for documents
lastUpdatedOn2026-07-14T05:38:50.362+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0
criticalBlockerThemeVacuum

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

TaskDescriptionStatusOwnerDependencyBlocking?
PP-0003Fix and verify reactor bottom valvePO Under ProcessProcurement
Mr.Kailas
blocks: SSR-201 bottom valve must be fixed before SSR-201 no-load commissioning.Blocking
PP-0004Complete vacuum connection to reactorMaterial AwaitedEngineering / Procurement
Mr.Sharma Ji
blocks: SSR-201 vacuum connection must be complete before SSR-201 no-load commissioning.Blocking
PP-0005Complete scrubber / vent connection to reactorVendor MobilizedVendor
Mr.Reji (Vendor)
blocks: SSR-201 scrubber/vent connection must be complete before SSR-201 no-load commissioning.Blocking
PP-0006Complete hot water connection to reactor jacket / coilClosedEngineering
Mr.Sharma Ji
blocks: SSR-201 hot water connection must be complete before SSR-201 no-load commissioning.Cleared

Blocking / Downstream Tasks

TaskDescriptionStatusOwnerDependencyCurrent Effect
PP-0009Prepare and execute IQ/OQ package for reactorNot StartedProduction
Mr.Sharma Ji / Mr.Jain Ji
prerequisite: SSR-201 commissioning records are required before IQ/OQ execution.Blocking successor

Recent Update History

Jul 14, 2026, 5:38 AMUpdated by: SivaSource: Stakeholder update form

Remarks: waiting for Amir tanks Team, awaiting for documents

Old values

owner department
Engineering / Production
responsible person
remarks next action
revised target date
target completion date

New values

owner department
Vendor
responsible person
Amir Tanks
remarks next action
waiting for Amir tanks Team, awaiting for documents
revised target date
2026-07-30
target completion date
2026-07-15