PP-0008: Execute equipment installation checklist and no-load commissioning trial

Task Details

taskIdPP-0008
sourceCommissioning Expert Addition
workstreamEquipment
areaIntermediate
equipmentSystemSSR-201
capacitySize130
activityCategoryCommissioning
readinessGateCommissioning
activityDescriptionExecute equipment installation checklist and no-load commissioning trial
currentStatusNot Started
dashboardBucketNot Started
priorityCritical
ownerDepartmentEngineering / Production
responsiblePerson
vendorAgencyAmir Tanks
targetCompletionDate
revisedTargetDate
actualCompletionDate
dependencyPredecessorMechanical, utility, electrical, scrubber and vacuum readiness
blockertrue
blockingImpactedItemsSSR-201 qualification readiness
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaSigned commissioning checklist and trial run report.
remarksNextAction
lastUpdatedOn
updatedBy
daysToTarget
scheduleFlagBlocked
completionPercent0
criticalBlockerThemeVacuum

Stakeholder Task Update

Updates require DATA_SOURCE=supabase. CSV mode remains read-only.

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

TaskDescriptionStatusOwnerDependencyBlocking?
PP-0003Fix and verify reactor bottom valveNot StartedEngineering
Unassigned
blocks: SSR-201 bottom valve must be fixed before SSR-201 no-load commissioning.Blocking
PP-0004Complete vacuum connection to reactorPO Under ProcessEngineering / Procurement
Unassigned
blocks: SSR-201 vacuum connection must be complete before SSR-201 no-load commissioning.Blocking
PP-0005Complete scrubber / vent connection to reactorPO Under ProcessEngineering / Procurement
Unassigned
blocks: SSR-201 scrubber/vent connection must be complete before SSR-201 no-load commissioning.Blocking
PP-0006Complete hot water connection to reactor jacket / coilNot StartedEngineering
Unassigned
blocks: SSR-201 hot water connection must be complete before SSR-201 no-load commissioning.Blocking

Blocking / Downstream Tasks

TaskDescriptionStatusOwnerDependencyCurrent Effect
PP-0009Prepare and execute IQ/OQ package for reactorNot StartedQA / Validation
Unassigned
prerequisite: SSR-201 commissioning records are required before IQ/OQ execution.Blocking successor

Recent Update History

Update history is available when DATA_SOURCE=supabase is enabled. CSV mode remains read-only.