Pilot Plant TrackerChecking session…
← Back to Master Task RegisterDashboard

Data source: Supabase

PP-0004: Complete vacuum connection to reactor

Task Details

taskIdPP-0004
sourceSheet2 transformed
workstreamUtility
areaIntermediate
equipmentSystemSSR-201
capacitySize130
activityCategoryPiping / Utility
readinessGateUtility Completion
activityDescriptionComplete vacuum connection to reactor
currentStatusMaterial Awaited
dashboardBucketProcurement Pending
priorityCritical
ownerDepartmentEngineering / Procurement
responsiblePersonMr.Sharma Ji
vendorAgencyVacuum / Piping Vendor
targetCompletionDate2026-07-30
revisedTargetDate
actualCompletionDate
dependencyPredecessorLow/high vacuum piping procurement and installation
blockertrue
blockingImpactedItemsSS reactor commissioning and vacuum hold test
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaVacuum line connected, tagged, leak-tested, and vacuum hold test recorded.
remarksNextActionwork to be started after receipt of material
lastUpdatedOn2026-07-14T05:12:07.892+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0.3
criticalBlockerThemeVacuum

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

TaskDescriptionStatusOwnerDependencyCurrent Effect
PP-0008Execute equipment installation checklist and no-load commissioning trialNot StartedVendor
Amir Tanks
blocks: SSR-201 vacuum connection must be complete before SSR-201 no-load commissioning.Blocking successor

Recent Update History

Jul 14, 2026, 5:12 AMUpdated by: SivaSource: Stakeholder update form

Remarks: work to be started after receipt of material

Old values

current status
PO Under Process
responsible person
remarks next action
Original sheet combines vacuum and scrubber connection.
target completion date

New values

current status
Material Awaited
responsible person
Mr.Sharma Ji
remarks next action
work to be started after receipt of material
target completion date
2026-07-30