Remarks: Material received, work under progress
Old values
- current status
- Material Awaited
New values
- current status
- Work In Progress
Data source: Supabase
| taskId | PP-0004 |
|---|---|
| source | Sheet2 transformed |
| workstream | Utility |
| area | Intermediate |
| equipmentSystem | SSR-201 |
| capacitySize | 130 |
| activityCategory | Piping / Utility |
| readinessGate | Utility Completion |
| activityDescription | Complete vacuum connection to reactor |
| currentStatus | Work In Progress |
| dashboardBucket | In Progress |
| priority | Critical |
| ownerDepartment | Engineering / Procurement |
| responsiblePerson | Mr.Sharma Ji |
| vendorAgency | Vacuum / Piping Vendor |
| targetCompletionDate | 2026-07-30 |
| revisedTargetDate | |
| actualCompletionDate | |
| dependencyPredecessor | Low/high vacuum piping procurement and installation |
| blocker | true |
| blockingImpactedItems | SS reactor commissioning and vacuum hold test |
| commissioningImpact | true |
| qualificationImpact | true |
| evidenceAcceptanceCriteria | Vacuum line connected, tagged, leak-tested, and vacuum hold test recorded. |
| remarksNextAction | work to be started after receipt of material |
| lastUpdatedOn | 2026-08-03T07:45:06.501+00:00 |
| updatedBy | Siva |
| daysToTarget | |
| scheduleFlag | Blocked |
| completionPercent | 0.55 |
| criticalBlockerTheme | Vacuum |
No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.
Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.
No upstream task dependencies are mapped for this task.
| Task | Description | Status | Owner | Dependency | Current Effect |
|---|---|---|---|---|---|
| PP-0008 | Execute equipment installation checklist and no-load commissioning trial | Not Started | Vendor Amir Tanks | blocks: SSR-201 vacuum connection must be complete before SSR-201 no-load commissioning. | Blocking successor |
Remarks: Material received, work under progress
Remarks: work to be started after receipt of material