Remarks: activity completed
Old values
- blocker
- Yes
- current status
- Work In Progress
- remarks next action
- Originally Amir tanks to be completed, but Thinq handling due to delay in work
New values
- blocker
- No
- current status
- Closed
- remarks next action
- —
Data source: Supabase
| taskId | PP-0006 |
|---|---|
| source | Sheet2 transformed |
| workstream | Utility |
| area | Intermediate |
| equipmentSystem | SSR-201 |
| capacitySize | 130 |
| activityCategory | Piping / Utility |
| readinessGate | Utility Completion |
| activityDescription | Complete hot water connection to reactor jacket / coil |
| currentStatus | Closed |
| dashboardBucket | Closed |
| priority | Critical |
| ownerDepartment | Engineering |
| responsiblePerson | Mr.Sharma Ji |
| vendorAgency | Amir Tanks |
| targetCompletionDate | |
| revisedTargetDate | |
| actualCompletionDate | |
| dependencyPredecessor | Hot water system installation and manifold readiness |
| blocker | false |
| blockingImpactedItems | Heating trial for SSRs |
| commissioningImpact | true |
| qualificationImpact | true |
| evidenceAcceptanceCriteria | Hot water connection completed, leak-tested, circulation verified. |
| remarksNextAction | |
| lastUpdatedOn | 2026-07-14T05:31:22.822+00:00 |
| updatedBy | Siva |
| daysToTarget | |
| scheduleFlag | Blocked |
| completionPercent | 1 |
| criticalBlockerTheme | Hot Water |
No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.
Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.
No upstream task dependencies are mapped for this task.
| Task | Description | Status | Owner | Dependency | Current Effect |
|---|---|---|---|---|---|
| PP-0008 | Execute equipment installation checklist and no-load commissioning trial | Not Started | Vendor Amir Tanks | blocks: SSR-201 hot water connection must be complete before SSR-201 no-load commissioning. | Predecessor cleared |
Remarks: activity completed
Remarks: Originally Amir tanks to be completed, but Thinq handling due to delay in work