PP-0006: Complete hot water connection to reactor jacket / coil

Task Details

taskIdPP-0006
sourceSheet2 transformed
workstreamUtility
areaIntermediate
equipmentSystemSSR-201
capacitySize130
activityCategoryPiping / Utility
readinessGateUtility Completion
activityDescriptionComplete hot water connection to reactor jacket / coil
currentStatusNot Started
dashboardBucketNot Started
priorityCritical
ownerDepartmentEngineering
responsiblePerson
vendorAgencyAmir Tanks
targetCompletionDate
revisedTargetDate
actualCompletionDate
dependencyPredecessorHot water system installation and manifold readiness
blockertrue
blockingImpactedItemsHeating trial for SSRs
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaHot water connection completed, leak-tested, circulation verified.
remarksNextAction
lastUpdatedOn
updatedBy
daysToTarget
scheduleFlagBlocked
completionPercent0
criticalBlockerThemeHot Water

Stakeholder Task Update

Updates require DATA_SOURCE=supabase. CSV mode remains read-only.

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

TaskDescriptionStatusOwnerDependencyCurrent Effect
PP-0008Execute equipment installation checklist and no-load commissioning trialNot StartedEngineering / Production
Unassigned
blocks: SSR-201 hot water connection must be complete before SSR-201 no-load commissioning.Blocking successor

Recent Update History

Update history is available when DATA_SOURCE=supabase is enabled. CSV mode remains read-only.