PP-0009: Prepare and execute IQ/OQ package for reactor

Task Details

taskIdPP-0009
sourceCommissioning Expert Addition
workstreamQualification
areaIntermediate
equipmentSystemSSR-201
capacitySize130
activityCategoryQualification
readinessGateQualification
activityDescriptionPrepare and execute IQ/OQ package for reactor
currentStatusNot Started
dashboardBucketNot Started
priorityHigh
ownerDepartmentProduction
responsiblePersonMr.Sharma Ji / Mr.Jain Ji
vendorAgency
targetCompletionDate2026-08-05
revisedTargetDate
actualCompletionDate
dependencyPredecessorApproved drawings, calibration, commissioning records and SOPs
blockerfalse
blockingImpactedItemsSSR-201 ready-to-operate approval
commissioningImpactfalse
qualificationImpacttrue
evidenceAcceptanceCriteriaApproved IQ/OQ protocol, executed report, deviation closure and QA approval.
remarksNextActionAmir tanks presence required during qualification
lastUpdatedOn2026-07-14T05:41:07.43+00:00
updatedBySiva
daysToTarget
scheduleFlagNo Target
completionPercent0
criticalBlockerTheme

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

TaskDescriptionStatusOwnerDependencyBlocking?
PP-0008Execute equipment installation checklist and no-load commissioning trialNot StartedVendor
Amir Tanks
prerequisite: SSR-201 commissioning records are required before IQ/OQ execution.Blocking

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 14, 2026, 5:41 AMUpdated by: SivaSource: Stakeholder update form

Remarks: Amir tanks presence required during qualification

Old values

owner department
QA / Validation
responsible person
remarks next action
target completion date

New values

owner department
Production
responsible person
Mr.Sharma Ji / Mr.Jain Ji
remarks next action
Amir tanks presence required during qualification
target completion date
2026-08-05