PP-0005: Complete scrubber / vent connection to reactor

Task Details

taskIdPP-0005
sourceSheet2 transformed
workstreamSafety / EHS
areaIntermediate
equipmentSystemSSR-201
capacitySize130
activityCategoryPiping / Venting
readinessGateSafety Readiness
activityDescriptionComplete scrubber / vent connection to reactor
currentStatusVendor Mobilized
dashboardBucketIn Progress
priorityCritical
ownerDepartmentVendor
responsiblePersonMr.Reji (Vendor)
vendorAgencyScrubber / Piping Vendor
targetCompletionDate2026-07-30
revisedTargetDate
actualCompletionDate
dependencyPredecessorScrubber piping fabrication and header connection
blockertrue
blockingImpactedItemsSafe reactor trial and vent handling readiness
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaScrubber/vent line connected, leak-tested, flow path verified, and emergency vent route checked.
remarksNextActionMaterial received, work to be started
lastUpdatedOn2026-07-14T05:17:06.099+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0.4
criticalBlockerThemeScrubber

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

TaskDescriptionStatusOwnerDependencyCurrent Effect
PP-0008Execute equipment installation checklist and no-load commissioning trialNot StartedVendor
Amir Tanks
blocks: SSR-201 scrubber/vent connection must be complete before SSR-201 no-load commissioning.Blocking successor

Recent Update History

Jul 14, 2026, 5:17 AMUpdated by: SivaSource: Stakeholder update form

Remarks: Material received, work to be started

Old values

current status
PO Under Process
owner department
Engineering / Procurement
responsible person
remarks next action
Original sheet combines vacuum and scrubber connection.
target completion date

New values

current status
Vendor Mobilized
owner department
Vendor
responsible person
Mr.Reji (Vendor)
remarks next action
Material received, work to be started
target completion date
2026-07-30