Remarks: Planned from next week from 20/07/2026
Old values
- target completion date
- 2026-07-25
New values
- target completion date
- 2026-07-30
Data source: Supabase
| taskId | PP-0060 |
|---|---|
| source | Sheet2 transformed |
| workstream | Equipment |
| area | Intermediate |
| equipmentSystem | GLR-201 |
| capacitySize | 100 |
| activityCategory | Mechanical / Piping |
| readinessGate | Mechanical Completion |
| activityDescription | Install and fix glass condensing system / condenser |
| currentStatus | Received |
| dashboardBucket | In Progress |
| priority | Critical |
| ownerDepartment | Vendor |
| responsiblePerson | Surya Scientific (Vendor) |
| vendorAgency | Amir Tanks / Glass Condensing Vendor |
| targetCompletionDate | 2026-07-30 |
| revisedTargetDate | |
| actualCompletionDate | |
| dependencyPredecessor | Utility pipeline fabrication and insulation completion |
| blocker | true |
| blockingImpactedItems | GLR reflux, distillation and commissioning |
| commissioningImpact | true |
| qualificationImpact | true |
| evidenceAcceptanceCriteria | Condenser installed, aligned, connected and leak-tested. |
| remarksNextAction | Planned from next week from 20/07/2026 |
| lastUpdatedOn | 2026-07-14T06:02:33.482+00:00 |
| updatedBy | Siva |
| daysToTarget | 19 |
| scheduleFlag | Blocked |
| completionPercent | 0.5 |
| criticalBlockerTheme | Insulation |
No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.
Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.
No upstream task dependencies are mapped for this task.
| Task | Description | Status | Owner | Dependency | Current Effect |
|---|---|---|---|---|---|
| PP-0061 | Execute GLR installation checklist and no-load commissioning trial | Not Started | Vendor HLE Glass Coat (Vendor) | blocks: GLR-201 condenser installation must be complete before GLR-201 no-load commissioning. | Blocking successor |
Remarks: Planned from next week from 20/07/2026
Remarks: Planned from next week from 20/07/2026