PP-0060: Install and fix glass condensing system / condenser

Task Details

taskIdPP-0060
sourceSheet2 transformed
workstreamEquipment
areaIntermediate
equipmentSystemGLR-201
capacitySize100
activityCategoryMechanical / Piping
readinessGateMechanical Completion
activityDescriptionInstall and fix glass condensing system / condenser
currentStatusReceived
dashboardBucketIn Progress
priorityCritical
ownerDepartmentVendor
responsiblePersonSurya Scientific (Vendor)
vendorAgencyAmir Tanks / Glass Condensing Vendor
targetCompletionDate2026-07-30
revisedTargetDate
actualCompletionDate
dependencyPredecessorUtility pipeline fabrication and insulation completion
blockertrue
blockingImpactedItemsGLR reflux, distillation and commissioning
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaCondenser installed, aligned, connected and leak-tested.
remarksNextActionPlanned from next week from 20/07/2026
lastUpdatedOn2026-07-14T06:02:33.482+00:00
updatedBySiva
daysToTarget19
scheduleFlagBlocked
completionPercent0.5
criticalBlockerThemeInsulation

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

TaskDescriptionStatusOwnerDependencyCurrent Effect
PP-0061Execute GLR installation checklist and no-load commissioning trialNot StartedVendor
HLE Glass Coat (Vendor)
blocks: GLR-201 condenser installation must be complete before GLR-201 no-load commissioning.Blocking successor

Recent Update History

Jul 14, 2026, 6:02 AMUpdated by: SivaSource: Stakeholder update form

Remarks: Planned from next week from 20/07/2026

Old values

target completion date
2026-07-25

New values

target completion date
2026-07-30
Jul 14, 2026, 6:01 AMUpdated by: SivaSource: Stakeholder update form

Remarks: Planned from next week from 20/07/2026

Old values

current status
Not Started
owner department
Engineering
responsible person
remarks next action
Target captured from source sheet: 22-Jul-2026.
target completion date
2026-07-22

New values

current status
Received
owner department
Vendor
responsible person
Surya Scientific (Vendor)
remarks next action
Planned from next week from 20/07/2026
target completion date
2026-07-25