Remarks: completed
Old values
- current status
- Not Started
New values
- current status
- Closed
Data source: Supabase
| taskId | PP-0061 |
|---|---|
| source | Commissioning Expert Addition |
| workstream | Equipment |
| area | Intermediate |
| equipmentSystem | GLR-201 |
| capacitySize | 100 |
| activityCategory | Commissioning |
| readinessGate | Commissioning |
| activityDescription | Execute GLR installation checklist and no-load commissioning trial |
| currentStatus | Closed |
| dashboardBucket | Closed |
| priority | Critical |
| ownerDepartment | Vendor |
| responsiblePerson | HLE Glass Coat (Vendor) |
| vendorAgency | GLR Vendor |
| targetCompletionDate | 2026-08-05 |
| revisedTargetDate | |
| actualCompletionDate | |
| dependencyPredecessor | Bottom valve, condenser, utilities, vacuum, scrubber and electrical readiness |
| blocker | true |
| blockingImpactedItems | GLR-201 qualification readiness |
| commissioningImpact | true |
| qualificationImpact | true |
| evidenceAcceptanceCriteria | Signed commissioning checklist and trial run report. |
| remarksNextAction | waiting for completion of utility and other activities |
| lastUpdatedOn | 2026-08-26T10:20:30.768+00:00 |
| updatedBy | Siva |
| daysToTarget | |
| scheduleFlag | Blocked |
| completionPercent | 1 |
| criticalBlockerTheme | Vacuum |
No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.
Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.
| Task | Description | Status | Owner | Dependency | Blocking? |
|---|---|---|---|---|---|
| PP-0060 | Install and fix glass condensing system / condenser | Work In Progress | Vendor Surya Scientific (Vendor) | blocks: GLR-201 condenser installation must be complete before GLR-201 no-load commissioning. | Blocking |
| Task | Description | Status | Owner | Dependency | Current Effect |
|---|---|---|---|---|---|
| PP-0062 | Prepare and execute IQ/OQ package for GLR | Not Started | Production Mr.Sharma Ji / Mr.Jain Ji | prerequisite: GLR-201 commissioning records are required before IQ/OQ execution. | Predecessor cleared |
Remarks: completed
Remarks: waiting for completion of utility and other activities