Master Task Register

Filter/search by task code, description, workstream, area, equipment, status, priority, owner, vendor, manual blocker, task dependency, and impact fields. CSV export preserves seed core columns.

Data source: Supabase

Export filtered CSVClear filtersDashboard

Showing Equipment: GLR-2048 of 241 tasks

TaskWorkstreamAreaEquipmentDescriptionStatusPriorityOwnerTargetManual BlockerDependency BlockedBlocked ByBlockingC ImpactQ Impact
PP-0079EquipmentIntermediateGLR-204Receive and install glass-lined reactor in final positionClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0080EquipmentIntermediateGLR-204Fix and verify GLR bottom valveWork In ProgressCriticalEngineering
Mr.Sharma Ji
2026-07-25YesNo00YesYes
PP-0081UtilityIntermediateGLR-204Complete vacuum connection to GLRMaterial AwaitedCriticalProcurement
Mr.Kailas
2026-07-25YesNo00YesYes
PP-0082Safety / EHSIntermediateGLR-204Complete scrubber / vent connection to GLRReceivedCriticalVendor
Mr.Reji (Vendor)
2026-07-25YesNo00YesYes
PP-0083UtilityIntermediateGLR-204Complete hot water connection to GLR jacket / coilClosedCriticalEngineering
Mr.Sharma Ji
No TargetYesNo00YesYes
PP-0084EquipmentIntermediateGLR-204Install and fix glass condensing system / condenserReceivedCriticalVendor
Surya Scientific (Vendor)
2026-07-30YesNo00YesYes
PP-0085EquipmentIntermediateGLR-204Execute GLR installation checklist and no-load commissioning trialNot StartedCriticalVendor
HLE Glass Coat (Vendor)
2026-08-05YesNo00YesYes
PP-0086QualificationIntermediateGLR-204Prepare and execute IQ/OQ package for GLRNot StartedHighProduction
Mr.Sharma Ji / Mr.Jain Ji
2026-08-05YesNo00NoYes

Imported columns supported: 31. Closed and qualified tasks remain visible unless an open-only filter is selected.