Master Task Register
Filter/search by task code, description, workstream, area, equipment, status, priority, owner, vendor, manual blocker, task dependency, and impact fields. CSV export preserves seed core columns.
Data source: CSV — CSV fallback active because Supabase read failed. Unable to read Supabase tasks: TypeError: fetch failed
Showing Equipment: SSR-202 — 9 of 241 tasks
| Task | Workstream | Area | Equipment | Description | Status | Priority | Owner | Target | Manual Blocker | Dependency Blocked | Blocked By | Blocking | C Impact | Q Impact |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| PP-0010 | Equipment | Intermediate | SSR-202 | Receive and install stainless steel reactor in final position | Closed | High | Engineering Unassigned | No Target | No | No | 0 | 0 | No | No |
| PP-0011 | Documentation | Intermediate | SSR-202 | Receive approved reactor drawings from Amir Tanks | Material Awaited | High | Engineering Unassigned | No Target | Yes | No | 0 | 0 | No | Yes |
| PP-0012 | Equipment | Intermediate | SSR-202 | Fix and verify reactor bottom valve | Not Started | Critical | Engineering Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0013 | Utility | Intermediate | SSR-202 | Complete vacuum connection to reactor | PO Under Process | Critical | Engineering / Procurement Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0014 | Safety / EHS | Intermediate | SSR-202 | Complete scrubber / vent connection to reactor | PO Under Process | Critical | Engineering / Procurement Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0015 | Utility | Intermediate | SSR-202 | Complete hot water connection to reactor jacket / coil | Not Started | Critical | Engineering Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0016 | Equipment | Intermediate | SSR-202 | Complete reflux lines and interconnecting piping | Work In Progress | Critical | Engineering Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0017 | Equipment | Intermediate | SSR-202 | Execute equipment installation checklist and no-load commissioning trial | Not Started | Critical | Engineering / Production Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0018 | Qualification | Intermediate | SSR-202 | Prepare and execute IQ/OQ package for reactor | Not Started | High | QA / Validation Unassigned | No Target | No | No | 0 | 0 | No | Yes |
Imported columns supported: 31. Closed and qualified tasks remain visible unless an open-only filter is selected.