Showing Equipment: SSR-2059 of 241 tasks

TaskWorkstreamAreaEquipmentDescriptionStatusPriorityOwnerTargetManual BlockerDependency BlockedBlocked ByBlockingC ImpactQ Impact
PP-0037EquipmentIntermediateSSR-205Receive and install stainless steel reactor in final positionClosedHighEngineering
Amir Tanks
No TargetNoNo00NoNo
PP-0038DocumentationIntermediateSSR-205Receive approved reactor drawings from Amir TanksMaterial AwaitedHighEngineering
Mr.Sharma Ji
2026-07-20YesNo00NoYes
PP-0039EquipmentIntermediateSSR-205Fix and verify reactor bottom valveClosedCriticalProcurement
Mr.Kailas
2026-07-16NoNo00YesYes
PP-0040UtilityIntermediateSSR-205Complete vacuum connection to reactorMaterial AwaitedCriticalEngineering / Procurement
Mr.Sharma Ji
2026-07-30YesNo00YesYes
PP-0041Safety / EHSIntermediateSSR-205Complete scrubber / vent connection to reactorVendor MobilizedCriticalVendor
Mr.Reji (Vendor)
2026-07-30YesNo00YesYes
PP-0042UtilityIntermediateSSR-205Complete hot water connection to reactor jacket / coilClosedCriticalEngineering
Mr.Sharma Ji
No TargetNoNo00YesYes
PP-0043EquipmentIntermediateSSR-205Complete reflux lines and interconnecting pipingWork In ProgressCriticalVendor
Amir Tanks
2026-07-22YesNo00YesYes
PP-0044EquipmentIntermediateSSR-205Execute equipment installation checklist and no-load commissioning trialNot StartedCriticalVendor
Amir Tanks
2026-07-30YesNo00YesYes
PP-0045QualificationIntermediateSSR-205Prepare and execute IQ/OQ package for reactorNot StartedHighProduction
Mr.Sharma Ji / Mr.Jain Ji
2026-08-05NoNo00NoYes