Master Task Register

Filter/search by task code, description, workstream, area, equipment, status, priority, owner, vendor, manual blocker, task dependency, and impact fields. CSV export preserves seed core columns.

Data source: Supabase

Export filtered CSVClear filtersDashboard

Showing Equipment: GLR-2028 of 241 tasks

TaskWorkstreamAreaEquipmentDescriptionStatusPriorityOwnerTargetManual BlockerDependency BlockedBlocked ByBlockingC ImpactQ Impact
PP-0063EquipmentIntermediateGLR-202Receive and install glass-lined reactor in final positionClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0064EquipmentIntermediateGLR-202Fix and verify GLR bottom valveWork In ProgressCriticalEngineering
Mr.Sharma Ji
2026-07-25YesNo00YesYes
PP-0065UtilityIntermediateGLR-202Complete vacuum connection to GLRMaterial AwaitedCriticalProcurement
Mr.Kailas
2026-07-25YesNo00YesYes
PP-0066Safety / EHSIntermediateGLR-202Complete scrubber / vent connection to GLRReceivedCriticalVendor
Mr.Reji (Vendor)
2026-07-25YesNo00YesYes
PP-0067UtilityIntermediateGLR-202Complete hot water connection to GLR jacket / coilClosedCriticalEngineering
Mr.Sharma Ji
No TargetYesNo00YesYes
PP-0068EquipmentIntermediateGLR-202Install and fix glass condensing system / condenserReceivedCriticalVendor
Surya Scientific (Vendor)
2026-07-30YesNo00YesYes
PP-0069EquipmentIntermediateGLR-202Execute GLR installation checklist and no-load commissioning trialNot StartedCriticalVendor
HLE Glass Coat (Vendor)
2026-08-05YesNo00YesYes
PP-0070QualificationIntermediateGLR-202Prepare and execute IQ/OQ package for GLRNot StartedHighProduction
Mr.Sharma Ji / Mr.Jain Ji
2026-08-05YesNo00NoYes

Imported columns supported: 31. Closed and qualified tasks remain visible unless an open-only filter is selected.