Pilot Plant TrackerChecking session…

Master Task Register

Filter/search by task code, description, workstream, area, equipment, status, priority, owner, vendor, manual blocker, task dependency, and impact fields. CSV export preserves seed core columns.

Data source: Supabase

Export filtered CSVClear filtersDashboard

Showing Area: Intermediate / Clean room10 of 241 tasks

TaskWorkstreamAreaEquipmentDescriptionStatusPriorityOwnerTargetManual BlockerDependency BlockedBlocked ByBlockingC ImpactQ Impact
PP-0222EquipmentIntermediate / Clean roomCentrifuge 1Verify Centrifuge 1 received at siteClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0223EquipmentIntermediate / Clean roomCentrifuge 1Install Centrifuge 1 in final locationUnder DiscussionCriticalProduction
RD & Production
2026-07-15NoNo00YesYes
PP-0224Electrical / InstrumentationIntermediate / Clean roomCentrifuge 1Complete electrical connection, earthing and safety interlock check for Centrifuge 1Not StartedCriticalElectrical / Instrumentation
Mr.Sharma Ji
2026-07-21YesNo00YesYes
PP-0225EquipmentIntermediate / Clean roomCentrifuge 1Execute no-load trial and functional checks for Centrifuge 1Not StartedHighEngineering / Production
Mr.Sharma Ji / Mr.Jain Ji
2026-07-31NoNo00YesYes
PP-0226QualificationIntermediate / Clean roomCentrifuge 1Prepare and execute IQ/OQ package for Centrifuge 1Not StartedHighProduction
Mr.Sharma Ji / Mr.Jain Ji
2026-08-05NoNo00NoYes
PP-0227EquipmentIntermediate / Clean roomCentrifuge 2Verify Centrifuge 2 received at siteClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0228EquipmentIntermediate / Clean roomCentrifuge 2Install Centrifuge 2 in final locationNot StartedCriticalEngineering
Unassigned
No TargetYesNo00YesYes
PP-0229Electrical / InstrumentationIntermediate / Clean roomCentrifuge 2Complete electrical connection, earthing and safety interlock check for Centrifuge 2Not StartedCriticalElectrical / Instrumentation
Unassigned
No TargetYesNo00YesYes
PP-0230EquipmentIntermediate / Clean roomCentrifuge 2Execute no-load trial and functional checks for Centrifuge 2Not StartedHighEngineering / Production
Unassigned
No TargetNoNo00YesYes
PP-0231QualificationIntermediate / Clean roomCentrifuge 2Prepare and execute IQ/OQ package for Centrifuge 2Not StartedHighQA / Validation
Unassigned
No TargetNoNo00NoYes

Imported columns supported: 31. Closed and qualified tasks remain visible unless an open-only filter is selected.