Master Task Register
Filter/search by task code, description, workstream, area, equipment, status, priority, owner, vendor, manual blocker, task dependency, and impact fields. CSV export preserves seed core columns.
Data source: Supabase
Showing Equipment: Hydrogenation Area — 6 of 241 tasks
| Task | Workstream | Area | Equipment | Description | Status | Priority | Owner | Target | Manual Blocker | Dependency Blocked | Blocked By | Blocking | C Impact | Q Impact |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| PP-0189 | Hydrogenation | Hydrogenation Area | Hydrogenation Area | Complete hydrogenation area utility pipeline work | Work In Progress | Critical | Engineering Mr.Sharma Ji | 2026-08-15 | Yes | No | 0 | 0 | Yes | Yes |
| PP-0190 | Hydrogenation | Hydrogenation Area | Hydrogenation Area | Complete hydrogenation area civil work | Under Discussion | Critical | Vendor Sri Ram Enterprises | 2026-08-31 | Yes | No | 0 | 0 | Yes | Yes |
| PP-0196 | Hydrogenation | Hydrogenation Area | Hydrogenation Area | Verify flameproof electrical fittings, earthing and bonding | Not Started | Critical | Engineering Mr.Sharma Ji | 2026-08-10 | Yes | No | 0 | 0 | Yes | Yes |
| PP-0197 | Hydrogenation | Hydrogenation Area | Hydrogenation Area | Install/verify hydrogen gas detection and ventilation | Not Started | Critical | Engineering Mr.Sharma Ji | 2026-08-31 | Yes | No | 0 | 0 | Yes | Yes |
| PP-0198 | Hydrogenation | Hydrogenation Area | Hydrogenation Area | Prepare purging, inerting and emergency response SOPs | Not Started | Critical | Production Mr.Nikhil sir / Mr.Jain / Mr.Bagal | 2026-09-15 | No | No | 0 | 0 | Yes | Yes |
| PP-0199 | Hydrogenation | Hydrogenation Area | Hydrogenation Area | Complete EHS pre-startup safety review for hydrogenation | Not Started | Critical | EHS Production / Safety | No Target | Yes | No | 0 | 0 | Yes | Yes |
Imported columns supported: 31. Closed and qualified tasks remain visible unless an open-only filter is selected.