Master Task Register

Filter/search by task code, description, workstream, area, equipment, status, priority, owner, vendor, manual blocker, task dependency, and impact fields. CSV export preserves seed core columns.

Data source: Supabase

Export filtered CSVClear filtersDashboard

Showing Equipment: SSR-2019 of 241 tasks

TaskWorkstreamAreaEquipmentDescriptionStatusPriorityOwnerTargetManual BlockerDependency BlockedBlocked ByBlockingC ImpactQ Impact
PP-0001EquipmentIntermediateSSR-201Receive and install stainless steel reactor in final positionClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0002DocumentationIntermediateSSR-201Receive approved reactor drawings from Amir TanksMaterial AwaitedHighEngineering
Mr.Sharma Ji
2026-07-20YesNo01NoYes
PP-0003EquipmentIntermediateSSR-201Fix and verify reactor bottom valvePO Under ProcessCriticalProcurement
Mr.Kailas
2026-07-16NoYes11YesYes
PP-0004UtilityIntermediateSSR-201Complete vacuum connection to reactorMaterial AwaitedCriticalEngineering / Procurement
Mr.Sharma Ji
2026-07-30YesNo01YesYes
PP-0005Safety / EHSIntermediateSSR-201Complete scrubber / vent connection to reactorVendor MobilizedCriticalVendor
Mr.Reji (Vendor)
2026-07-30YesNo01YesYes
PP-0006UtilityIntermediateSSR-201Complete hot water connection to reactor jacket / coilClosedCriticalEngineering
Mr.Sharma Ji
No TargetNoNo01YesYes
PP-0007EquipmentIntermediateSSR-201Complete reflux lines and interconnecting pipingWork In ProgressCriticalVendor
Amir Tanks
2026-07-22YesNo00YesYes
PP-0008EquipmentIntermediateSSR-201Execute equipment installation checklist and no-load commissioning trialNot StartedCriticalVendor
Amir Tanks
2026-07-30YesYes41YesYes
PP-0009QualificationIntermediateSSR-201Prepare and execute IQ/OQ package for reactorNot StartedHighProduction
Mr.Sharma Ji / Mr.Jain Ji
2026-08-05NoYes10NoYes

Imported columns supported: 31. Closed and qualified tasks remain visible unless an open-only filter is selected.