Master Task Register
Filter/search by task code, description, workstream, area, equipment, status, priority, owner, vendor, manual blocker, task dependency, and impact fields. CSV export preserves seed core columns.
Data source: Supabase
Showing Equipment: SSR-201 — 9 of 241 tasks
| Task | Workstream | Area | Equipment | Description | Status | Priority | Owner | Target | Manual Blocker | Dependency Blocked | Blocked By | Blocking | C Impact | Q Impact |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| PP-0001 | Equipment | Intermediate | SSR-201 | Receive and install stainless steel reactor in final position | Closed | High | Engineering Unassigned | No Target | No | No | 0 | 0 | No | No |
| PP-0002 | Documentation | Intermediate | SSR-201 | Receive approved reactor drawings from Amir Tanks | Material Awaited | High | Engineering Mr.Sharma Ji | 2026-07-20 | Yes | No | 0 | 1 | No | Yes |
| PP-0003 | Equipment | Intermediate | SSR-201 | Fix and verify reactor bottom valve | PO Under Process | Critical | Procurement Mr.Kailas | 2026-07-16 | No | Yes | 1 | 1 | Yes | Yes |
| PP-0004 | Utility | Intermediate | SSR-201 | Complete vacuum connection to reactor | Material Awaited | Critical | Engineering / Procurement Mr.Sharma Ji | 2026-07-30 | Yes | No | 0 | 1 | Yes | Yes |
| PP-0005 | Safety / EHS | Intermediate | SSR-201 | Complete scrubber / vent connection to reactor | Vendor Mobilized | Critical | Vendor Mr.Reji (Vendor) | 2026-07-30 | Yes | No | 0 | 1 | Yes | Yes |
| PP-0006 | Utility | Intermediate | SSR-201 | Complete hot water connection to reactor jacket / coil | Closed | Critical | Engineering Mr.Sharma Ji | No Target | No | No | 0 | 1 | Yes | Yes |
| PP-0007 | Equipment | Intermediate | SSR-201 | Complete reflux lines and interconnecting piping | Work In Progress | Critical | Vendor Amir Tanks | 2026-07-22 | Yes | No | 0 | 0 | Yes | Yes |
| PP-0008 | Equipment | Intermediate | SSR-201 | Execute equipment installation checklist and no-load commissioning trial | Not Started | Critical | Vendor Amir Tanks | 2026-07-30 | Yes | Yes | 4 | 1 | Yes | Yes |
| PP-0009 | Qualification | Intermediate | SSR-201 | Prepare and execute IQ/OQ package for reactor | Not Started | High | Production Mr.Sharma Ji / Mr.Jain Ji | 2026-08-05 | No | Yes | 1 | 0 | No | Yes |
Imported columns supported: 31. Closed and qualified tasks remain visible unless an open-only filter is selected.