Pilot Plant TrackerChecking session…
Dashboard

Dependencies

Task dependencies are predecessor/successor relationships between real task IDs. DEP-001, DEP-002, etc. are dependency themes / blocker categories only; they are not task IDs.

Task Dependency Graph

A task is dependency-blocked when any predecessor task is still open. This is shown separately from the manual blocker flag.

Predecessor TaskSuccessor TaskTypeDescriptionCritical?Derived Status
PP-0002
Receive approved reactor drawings from Amir Tanks
PP-0003
Fix and verify reactor bottom valve
prerequisiteApproved vendor drawings support SSR-201 bottom valve installation verification.YesBlocking
PP-0003
Fix and verify reactor bottom valve
PP-0008
Execute equipment installation checklist and no-load commissioning trial
blocksSSR-201 bottom valve must be fixed before SSR-201 no-load commissioning.YesBlocking
PP-0004
Complete vacuum connection to reactor
PP-0008
Execute equipment installation checklist and no-load commissioning trial
blocksSSR-201 vacuum connection must be complete before SSR-201 no-load commissioning.YesBlocking
PP-0005
Complete scrubber / vent connection to reactor
PP-0008
Execute equipment installation checklist and no-load commissioning trial
blocksSSR-201 scrubber/vent connection must be complete before SSR-201 no-load commissioning.YesBlocking
PP-0006
Complete hot water connection to reactor jacket / coil
PP-0008
Execute equipment installation checklist and no-load commissioning trial
blocksSSR-201 hot water connection must be complete before SSR-201 no-load commissioning.YesCleared
PP-0008
Execute equipment installation checklist and no-load commissioning trial
PP-0009
Prepare and execute IQ/OQ package for reactor
prerequisiteSSR-201 commissioning records are required before IQ/OQ execution.YesBlocking
PP-0060
Install and fix glass condensing system / condenser
PP-0061
Execute GLR installation checklist and no-load commissioning trial
blocksGLR-201 condenser installation must be complete before GLR-201 no-load commissioning.YesBlocking
PP-0061
Execute GLR installation checklist and no-load commissioning trial
PP-0062
Prepare and execute IQ/OQ package for GLR
prerequisiteGLR-201 commissioning records are required before IQ/OQ execution.YesBlocking
PP-0155
Complete line tagging, valve tagging, direction marking and pressure/leak testing for utility manifold - gl reactors
PP-0156
Update as-built drawing for utility manifold - gl reactors
prerequisiteUtility manifold leak/pressure testing supports the as-built drawing update.NoBlocking
PP-0211
Compile leak test, pressure test and vacuum hold records
PP-0212
Prepare IQ protocols for all critical equipment and utilities
prerequisiteLeak, pressure, and vacuum-hold records support the final handover pack.NoBlocking

Task Dependency Counts

TaskBlocked by countBlocking countOpen upstream blocker?
PP-000841Yes
PP-000311Yes
PP-006111Yes
PP-000910Yes
PP-006210Yes
PP-015610Yes
PP-021210Yes
PP-000201No
PP-000401No
PP-000501No
PP-000601No
PP-006001No
PP-015501No
PP-021101No

Dependency Themes / Blocker Categories

These DEP rows are thematic blockers imported from the commissioning blocker map. Clicking a theme searches related task text and blocker-theme fields; results are inferred/theme-related, not direct task records.

Theme IDTheme / Blocker CategoryDownstream ActivityImpacted Equipment / AreaImpact TypeCritical?OwnerStatusNext Action
DEP-001Insulation completionChilled water / chilled brine commissioningChilled Water Plant, Chilled Brine Plant, GLRs, condensers, hot water/steamUtility commissioning blockerYesEngineering / ProcurementOpenRelease PO, mobilize insulation vendor, inspect insulation.
DEP-002Chilled water / brine commissioningGLR condenser installation and GLR trialGLR-201 to GLR-205; glass condensing systemEquipment commissioning blockerYesEngineering / UtilityOpenCommission plants after insulation; document temperature/circulation performance.
DEP-003Low/high vacuum piping procurementVacuum connections and vacuum hold testsSSRs, GLRs, VTD-201, VTD-202Commissioning blockerYesEngineering / ProcurementOpenFinalize estimate, issue PO, install piping, complete vacuum hold test.
DEP-004Scrubber piping completionSafe reactor/VTD trial and venting readinessSSRs, GLRs, VTDs, scrubber systemSafety blockerYesEngineering / EHSOpenStart scrubber piping, connect equipment vents, commission scrubber.
DEP-005Hot water system installationHeating trials for reactors and VTDsSSRs, GLRs, VTD-201, VTD-202Utility commissioning blockerYesEngineering / UtilityOpenStart Amir Tanks work, connect circulation lines, leak test and commission.
DEP-006HVAC ducting completionCeiling closure and clean room qualificationClean room, washing area, packaging area, VTD-202 roomArea readiness blockerYesEngineering / HVACOpenComplete ducting, HEPA, return risers, testing and ceiling closure.
DEP-007Hydrogen/nitrogen manifold quote and POHydrogen reactor commissioningHydrogenation area and 250 L hydrogen reactorSafety/process blockerYesEngineering / Procurement / EHSOpenFinalize quotes, release PO, install gas manifold, pressure/leak test.
DEP-008Emergency exits and fire alarm completionPSSR and ready-to-operate approvalIntermediate area, clean room, whole pilot plantSafety readiness blockerYesEHS / EngineeringOpenFinalize clean room exit, install doors, commission fire alarm.
DEP-009Detailed area/GMP layout approvalQualification package and movement flow approvalClean room, intermediate areas, storage, emergency exitsGMP/qualification blockerYesEngineering / QA / EHSOpenObtain Atkarani layout, freeze movement flows and approve GMP layout.
DEP-010Working platform and stairs completionSafe access for reactor commissioning and operationReactor platforms and mezzanine floorSafety/access blockerYesEngineering / Fabrication VendorOpenComplete platform, stairs, handrails, ladders and access verification.