Showing Workstream: HVAC / Clean Room — 11 of 241 tasks
| Task | Workstream | Area | Equipment | Description | Status | Priority | Owner | Target | Manual Blocker | Dependency Blocked | Blocked By | Blocking | C Impact | Q Impact |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| PP-0112 | HVAC / Clean Room | Clean room | Washing area | Complete AHU installation / connection for washing area | Not Started | High | Engineering / HVAC Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0116 | HVAC / Clean Room | Clean room | Packaging area | Complete AHU installation / connection for packaging area | Not Started | High | Engineering / HVAC Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0172 | HVAC / Clean Room | Clean room | HVAC System | Complete HVAC ducting work in clean room | Work In Progress | Critical | Engineering / HVAC Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0173 | HVAC / Clean Room | Clean room | HVAC System | Install HEPA filters | Under Discussion | Critical | Engineering / HVAC Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0174 | HVAC / Clean Room | Clean room | HVAC System | Complete return risers | Under Discussion | Critical | Engineering / HVAC Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0175 | HVAC / Clean Room | Clean room | HVAC System | Perform duct leakage test | Not Started | High | Engineering / HVAC Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0176 | HVAC / Clean Room | Clean room | HVAC System | Perform air balancing and room pressure differential verification | Not Started | Critical | Engineering / HVAC Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0177 | HVAC / Clean Room | Clean room | HVAC System | Verify temperature and RH performance | Not Started | High | Engineering / HVAC Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0178 | HVAC / Clean Room | Clean room | HVAC System | Perform particle count and area classification | Not Started | Critical | Engineering / HVAC Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0179 | HVAC / Clean Room | Clean room | Ceiling System | Complete ceiling work after HVAC completion | Work In Progress | Critical | Vendor Pradham | 2026-07-31 | Yes | No | 0 | 0 | Yes | Yes |
| PP-0180 | HVAC / Clean Room | Clean room | Clean Room Area | Perform clean room cleaning and QA/EHS area release | Work In Progress | Critical | Vendor Mr.Sharma Ji / Pradham (Vendor) | 2026-08-10 | Yes | No | 0 | 0 | Yes | Yes |