Pilot Plant TrackerChecking session…

Master Task Register

Filter/search by task code, description, workstream, area, equipment, status, priority, owner, vendor, manual blocker, task dependency, and impact fields. CSV export preserves seed core columns.

Data source: Supabase

Export filtered CSVClear filtersDashboard

Showing Workstream: Electrical / Instrumentation16 of 241 tasks

TaskWorkstreamAreaEquipmentDescriptionStatusPriorityOwnerTargetManual BlockerDependency BlockedBlocked ByBlockingC ImpactQ Impact
PP-0100Electrical / InstrumentationClean roomVTD-202Verify VTD motor rotation, control panel, earthing, interlocks and instrumentsNot StartedCriticalElectrical / Instrumentation
Unassigned
No TargetYesNo00YesYes
PP-0108Electrical / InstrumentationIntermediateVTD-201Verify VTD motor rotation, control panel, earthing, interlocks and instrumentsNot StartedCriticalElectrical / Instrumentation
Unassigned
No TargetYesNo00YesYes
PP-0118Electrical / InstrumentationClean roomPackaging areaComplete electrical connectionsNot StartedHighElectrical / Instrumentation
Unassigned
No TargetNoNo00YesYes
PP-0122Electrical / InstrumentationIntermediateMilling and sifting areaComplete electrical connectionsNot StartedHighElectrical / Instrumentation
Unassigned
No TargetNoNo00YesNo
PP-0134Electrical / InstrumentationPilot plantLayer separation lampProvide electrical lamps for layer separationsClosedMediumElectrical / Instrumentation
Unassigned
No TargetNoNo00YesNo
PP-0181Electrical / InstrumentationPilot plantElectrical DistributionVerify major electrical connections and reactor push buttonsClosedHighEngineering
Mr.Sharma Ji
No TargetNoNo00YesYes
PP-0182Electrical / InstrumentationPilot plantElectrical DistributionComplete general lighting worksWork In ProgressHighEngineering
Mr.Sharma Ji
2026-07-31NoNo00YesYes
PP-0183Electrical / InstrumentationPilot plantElectrical DistributionInstall and verify emergency lightingWork In ProgressCriticalEngineering
Mr.Sharma Ji
2026-07-30YesNo00YesYes
PP-0184Electrical / InstrumentationPilot plantElectrical DistributionVerify equipment-wise earthing and bondingClosedCriticalEngineering
Mr.Sharma Ji
No TargetYesNo00YesYes
PP-0185Electrical / InstrumentationPilot plantElectrical DistributionPerform motor direction checks for all rotating equipmentWork In ProgressHighEngineering
Mr.Sharma Ji
2026-07-31NoNo00YesYes
PP-0186Electrical / InstrumentationPilot plantInstrumentationCalibrate temperature, pressure and vacuum instrumentsNot StartedHighElectrical / Instrumentation
Unassigned
No TargetNoNo00YesYes
PP-0187Electrical / InstrumentationPilot plantInstrumentationTest alarms, interlocks and emergency stopsNot StartedCriticalElectrical / Instrumentation
Unassigned
No TargetYesNo00YesYes
PP-0224Electrical / InstrumentationIntermediate / Clean roomCentrifuge 1Complete electrical connection, earthing and safety interlock check for Centrifuge 1Not StartedCriticalElectrical / Instrumentation
Mr.Sharma Ji
2026-07-21YesNo00YesYes
PP-0229Electrical / InstrumentationIntermediate / Clean roomCentrifuge 2Complete electrical connection, earthing and safety interlock check for Centrifuge 2Not StartedCriticalElectrical / Instrumentation
Unassigned
No TargetYesNo00YesYes
PP-0234Electrical / InstrumentationIntermediateSifterComplete electrical connection, earthing and safety interlock check for SifterNot StartedCriticalElectrical / Instrumentation
Unassigned
No TargetYesNo00YesYes
PP-0239Electrical / InstrumentationIntermediateMulti-millComplete electrical connection, earthing and safety interlock check for Multi-millNot StartedCriticalElectrical / Instrumentation
Unassigned
No TargetYesNo00YesYes

Imported columns supported: 31. Closed and qualified tasks remain visible unless an open-only filter is selected.