Master Task Register
Filter/search by task code, description, workstream, area, equipment, status, priority, owner, vendor, manual blocker, task dependency, and impact fields. CSV export preserves seed core columns.
Data source: Supabase
Showing Area: Clean room — 43 of 241 tasks
| Task | Workstream | Area | Equipment | Description | Status | Priority | Owner | Target | Manual Blocker | Dependency Blocked | Blocked By | Blocking | C Impact | Q Impact |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| PP-0046 | Equipment | Clean room | SSR-206 | Receive and install stainless steel reactor in final position | Closed | High | Engineering Unassigned | No Target | No | No | 0 | 0 | No | No |
| PP-0047 | Documentation | Clean room | SSR-206 | Receive approved reactor drawings from Amir Tanks | Material Awaited | High | Engineering Mr.Sharma Ji | 2026-07-20 | Yes | No | 0 | 0 | No | Yes |
| PP-0048 | Equipment | Clean room | SSR-206 | Fix and verify reactor bottom valve | PO Under Process | Critical | Procurement Mr.Kailas | 2026-07-16 | No | No | 0 | 0 | Yes | Yes |
| PP-0049 | Utility | Clean room | SSR-206 | Complete vacuum connection to reactor | Material Awaited | Critical | Engineering / Procurement Mr.Sharma Ji | 2026-07-30 | Yes | No | 0 | 0 | Yes | Yes |
| PP-0050 | Safety / EHS | Clean room | SSR-206 | Complete scrubber / vent connection to reactor | Vendor Mobilized | Critical | Vendor Mr.Reji (Vendor) | 2026-07-30 | Yes | No | 0 | 0 | Yes | Yes |
| PP-0051 | Utility | Clean room | SSR-206 | Complete hot water connection to reactor jacket / coil | Closed | Critical | Engineering Mr.Sharma Ji | No Target | No | No | 0 | 0 | Yes | Yes |
| PP-0052 | Equipment | Clean room | SSR-206 | Complete reflux lines and interconnecting piping | Work In Progress | Critical | Vendor Amir Tanks | 2026-07-22 | Yes | No | 0 | 0 | Yes | Yes |
| PP-0053 | Equipment | Clean room | SSR-206 | Execute equipment installation checklist and no-load commissioning trial | Not Started | Critical | Vendor Amir Tanks | 2026-07-30 | Yes | No | 0 | 0 | Yes | Yes |
| PP-0054 | Qualification | Clean room | SSR-206 | Prepare and execute IQ/OQ package for reactor | Not Started | High | Production Mr.Sharma Ji / Mr.Jain Ji | 2026-08-05 | No | No | 0 | 0 | No | Yes |
| PP-0087 | Equipment | Clean room | GLR-205 | Receive and install glass-lined reactor in final position | Closed | High | Engineering Unassigned | No Target | No | No | 0 | 0 | No | No |
| PP-0088 | Equipment | Clean room | GLR-205 | Fix and verify GLR bottom valve | Work In Progress | Critical | Engineering Mr.Sharma Ji | 2026-07-25 | Yes | No | 0 | 0 | Yes | Yes |
| PP-0089 | Utility | Clean room | GLR-205 | Complete vacuum connection to GLR | Material Awaited | Critical | Procurement Mr.Kailas | 2026-07-25 | Yes | No | 0 | 0 | Yes | Yes |
| PP-0090 | Safety / EHS | Clean room | GLR-205 | Complete scrubber / vent connection to GLR | Received | Critical | Vendor Mr.Reji (Vendor) | 2026-07-25 | Yes | No | 0 | 0 | Yes | Yes |
| PP-0091 | Utility | Clean room | GLR-205 | Complete hot water connection to GLR jacket / coil | Closed | Critical | Engineering Mr.Sharma Ji | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0092 | Equipment | Clean room | GLR-205 | Install and fix glass condensing system / condenser | Received | Critical | Vendor Surya Scientific (Vendor) | 2026-07-30 | Yes | No | 0 | 0 | Yes | Yes |
| PP-0093 | Equipment | Clean room | GLR-205 | Execute GLR installation checklist and no-load commissioning trial | Not Started | Critical | Vendor HLE Glass Coat (Vendor) | 2026-08-05 | Yes | No | 0 | 0 | Yes | Yes |
| PP-0094 | Qualification | Clean room | GLR-205 | Prepare and execute IQ/OQ package for GLR | Not Started | High | Production Mr.Sharma Ji / Mr.Jain Ji | 2026-08-05 | Yes | No | 0 | 0 | No | Yes |
| PP-0095 | Equipment | Clean room | VTD-202 | Receive VTD at site | Closed | High | Engineering Unassigned | No Target | No | No | 0 | 0 | No | No |
| PP-0096 | Area | Clean room | VTD-202 | Complete VTD room civil work: doors, AHU, air pipelines and flooring | Work In Progress | Critical | Engineering / HVAC Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0097 | Utility | Clean room | VTD-202 | Complete hot water connection to VTD | Not Started | Critical | Engineering Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0098 | Utility | Clean room | VTD-202 | Complete vacuum connection to VTD | PO Under Process | Critical | Engineering / Procurement Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0099 | Equipment | Clean room | VTD-202 | Verify solvent trap installation and drain / receiver connections | Not Started | High | Engineering Unassigned | No Target | No | No | 0 | 0 | Yes | Yes |
| PP-0100 | Electrical / Instrumentation | Clean room | VTD-202 | Verify VTD motor rotation, control panel, earthing, interlocks and instruments | Not Started | Critical | Electrical / Instrumentation Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0101 | Equipment | Clean room | VTD-202 | Execute empty trial, heating circulation check and vacuum hold test | Not Started | Critical | Engineering / Production Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0102 | Qualification | Clean room | VTD-202 | Prepare and execute IQ/OQ package for VTD | Not Started | High | QA / Validation Unassigned | No Target | No | No | 0 | 0 | No | Yes |
| PP-0111 | Area | Clean room | Washing area | Complete doors and area access readiness | Not Started | High | Engineering Unassigned | No Target | No | No | 0 | 0 | Yes | Yes |
| PP-0112 | HVAC / Clean Room | Clean room | Washing area | Complete AHU installation / connection for washing area | Not Started | High | Engineering / HVAC Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0113 | Utility | Clean room | Washing area | Complete water pipelines for washing area | Not Started | High | Engineering Unassigned | No Target | No | No | 0 | 0 | No | Yes |
| PP-0114 | Area | Clean room | Washing area | Complete flooring work | Not Started | High | Engineering Unassigned | No Target | No | No | 0 | 0 | Yes | Yes |
| PP-0115 | Area | Clean room | Packaging area | Complete doors and area access readiness | Not Started | High | Engineering Unassigned | No Target | No | No | 0 | 0 | Yes | Yes |
| PP-0116 | HVAC / Clean Room | Clean room | Packaging area | Complete AHU installation / connection for packaging area | Not Started | High | Engineering / HVAC Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0117 | Area | Clean room | Packaging area | Complete flooring work | Not Started | High | Engineering Unassigned | No Target | No | No | 0 | 0 | Yes | Yes |
| PP-0118 | Electrical / Instrumentation | Clean room | Packaging area | Complete electrical connections | Not Started | High | Electrical / Instrumentation Unassigned | No Target | No | No | 0 | 0 | Yes | Yes |
| PP-0132 | Safety / EHS | Clean room | Emergency exit | Finalize emergency exit location | Under Discussion | Critical | Engineering / EHS Siva | 2026-07-20 | Yes | No | 0 | 0 | Yes | Yes |
| PP-0172 | HVAC / Clean Room | Clean room | HVAC System | Complete HVAC ducting work in clean room | Work In Progress | Critical | Engineering / HVAC Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0173 | HVAC / Clean Room | Clean room | HVAC System | Install HEPA filters | Under Discussion | Critical | Engineering / HVAC Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0174 | HVAC / Clean Room | Clean room | HVAC System | Complete return risers | Under Discussion | Critical | Engineering / HVAC Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0175 | HVAC / Clean Room | Clean room | HVAC System | Perform duct leakage test | Not Started | High | Engineering / HVAC Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0176 | HVAC / Clean Room | Clean room | HVAC System | Perform air balancing and room pressure differential verification | Not Started | Critical | Engineering / HVAC Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0177 | HVAC / Clean Room | Clean room | HVAC System | Verify temperature and RH performance | Not Started | High | Engineering / HVAC Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0178 | HVAC / Clean Room | Clean room | HVAC System | Perform particle count and area classification | Not Started | Critical | Engineering / HVAC Unassigned | No Target | Yes | No | 0 | 0 | Yes | Yes |
| PP-0179 | HVAC / Clean Room | Clean room | Ceiling System | Complete ceiling work after HVAC completion | Work In Progress | Critical | Vendor Pradham | 2026-07-31 | Yes | No | 0 | 0 | Yes | Yes |
| PP-0180 | HVAC / Clean Room | Clean room | Clean Room Area | Perform clean room cleaning and QA/EHS area release | Work In Progress | Critical | Vendor Mr.Sharma Ji / Pradham (Vendor) | 2026-08-10 | Yes | No | 0 | 0 | Yes | Yes |
Imported columns supported: 31. Closed and qualified tasks remain visible unless an open-only filter is selected.