Pilot Plant TrackerChecking session…

Master Task Register

Filter/search by task code, description, workstream, area, equipment, status, priority, owner, vendor, manual blocker, task dependency, and impact fields. CSV export preserves seed core columns.

Data source: Supabase

Export filtered CSVClear filtersDashboard

Showing Workstream: Equipment — 64 of 241 tasks

TaskWorkstreamAreaEquipmentDescriptionStatusPriorityOwnerTargetManual BlockerDependency BlockedBlocked ByBlockingC ImpactQ Impact
PP-0001EquipmentIntermediateSSR-201Receive and install stainless steel reactor in final positionClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0003EquipmentIntermediateSSR-201Fix and verify reactor bottom valvePO Under ProcessCriticalProcurement
Mr.Kailas
2026-07-16NoYes11YesYes
PP-0007EquipmentIntermediateSSR-201Complete reflux lines and interconnecting pipingWork In ProgressCriticalVendor
Amir Tanks
2026-07-22YesNo00YesYes
PP-0008EquipmentIntermediateSSR-201Execute equipment installation checklist and no-load commissioning trialNot StartedCriticalVendor
Amir Tanks
2026-07-30YesYes41YesYes
PP-0010EquipmentIntermediateSSR-202Receive and install stainless steel reactor in final positionClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0012EquipmentIntermediateSSR-202Fix and verify reactor bottom valvePO Under ProcessCriticalProcurement
Mr.Kailas
2026-07-16NoNo00YesYes
PP-0016EquipmentIntermediateSSR-202Complete reflux lines and interconnecting pipingWork In ProgressCriticalVendor
Amir Tanks
2026-07-22YesNo00YesYes
PP-0017EquipmentIntermediateSSR-202Execute equipment installation checklist and no-load commissioning trialNot StartedCriticalVendor
Amir Tanks
2026-07-30YesNo00YesYes
PP-0019EquipmentIntermediateSSR-203Receive and install stainless steel reactor in final positionClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0021EquipmentIntermediateSSR-203Fix and verify reactor bottom valvePO Under ProcessCriticalProcurement
Mr.Kailas
2026-07-16NoNo00YesYes
PP-0025EquipmentIntermediateSSR-203Complete reflux lines and interconnecting pipingWork In ProgressCriticalVendor
Amir Tanks
2026-07-22YesNo00YesYes
PP-0026EquipmentIntermediateSSR-203Execute equipment installation checklist and no-load commissioning trialNot StartedCriticalVendor
Amir Tanks
2026-07-30YesNo00YesYes
PP-0028EquipmentIntermediateSSR-204Receive and install stainless steel reactor in final positionClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0030EquipmentIntermediateSSR-204Fix and verify reactor bottom valvePO Under ProcessCriticalProcurement
Mr.Kailas
2026-07-16NoNo00YesYes
PP-0034EquipmentIntermediateSSR-204Complete reflux lines and interconnecting pipingWork In ProgressCriticalVendor
Amir Tanks
2026-07-22YesNo00YesYes
PP-0035EquipmentIntermediateSSR-204Execute equipment installation checklist and no-load commissioning trialNot StartedCriticalVendor
Amir Tanks
2026-07-30YesNo00YesYes
PP-0037EquipmentIntermediateSSR-205Receive and install stainless steel reactor in final positionClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0039EquipmentIntermediateSSR-205Fix and verify reactor bottom valvePO Under ProcessCriticalProcurement
Mr.Kailas
2026-07-16NoNo00YesYes
PP-0043EquipmentIntermediateSSR-205Complete reflux lines and interconnecting pipingWork In ProgressCriticalVendor
Amir Tanks
2026-07-22YesNo00YesYes
PP-0044EquipmentIntermediateSSR-205Execute equipment installation checklist and no-load commissioning trialNot StartedCriticalVendor
Amir Tanks
2026-07-30YesNo00YesYes
PP-0046EquipmentClean roomSSR-206Receive and install stainless steel reactor in final positionClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0048EquipmentClean roomSSR-206Fix and verify reactor bottom valvePO Under ProcessCriticalProcurement
Mr.Kailas
2026-07-16NoNo00YesYes
PP-0052EquipmentClean roomSSR-206Complete reflux lines and interconnecting pipingWork In ProgressCriticalVendor
Amir Tanks
2026-07-22YesNo00YesYes
PP-0053EquipmentClean roomSSR-206Execute equipment installation checklist and no-load commissioning trialNot StartedCriticalVendor
Amir Tanks
2026-07-30YesNo00YesYes
PP-0055EquipmentIntermediateGLR-201Receive and install glass-lined reactor in final positionClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0056EquipmentIntermediateGLR-201Fix and verify GLR bottom valveWork In ProgressCriticalEngineering
Mr.Sharma Ji
2026-07-25YesNo00YesYes
PP-0060EquipmentIntermediateGLR-201Install and fix glass condensing system / condenserReceivedCriticalVendor
Surya Scientific (Vendor)
2026-07-30YesNo01YesYes
PP-0061EquipmentIntermediateGLR-201Execute GLR installation checklist and no-load commissioning trialNot StartedCriticalVendor
HLE Glass Coat (Vendor)
2026-08-05YesYes11YesYes
PP-0063EquipmentIntermediateGLR-202Receive and install glass-lined reactor in final positionClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0064EquipmentIntermediateGLR-202Fix and verify GLR bottom valveWork In ProgressCriticalEngineering
Mr.Sharma Ji
2026-07-25YesNo00YesYes
PP-0068EquipmentIntermediateGLR-202Install and fix glass condensing system / condenserReceivedCriticalVendor
Surya Scientific (Vendor)
2026-07-30YesNo00YesYes
PP-0069EquipmentIntermediateGLR-202Execute GLR installation checklist and no-load commissioning trialNot StartedCriticalVendor
HLE Glass Coat (Vendor)
2026-08-05YesNo00YesYes
PP-0071EquipmentIntermediateGLR-203Receive and install glass-lined reactor in final positionClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0072EquipmentIntermediateGLR-203Fix and verify GLR bottom valveWork In ProgressCriticalEngineering
Mr.Sharma Ji
2026-07-25YesNo00YesYes
PP-0076EquipmentIntermediateGLR-203Install and fix glass condensing system / condenserReceivedCriticalVendor
Surya Scientific (Vendor)
2026-07-30YesNo00YesYes
PP-0077EquipmentIntermediateGLR-203Execute GLR installation checklist and no-load commissioning trialNot StartedCriticalVendor
HLE Glass Coat (Vendor)
2026-08-05YesNo00YesYes
PP-0079EquipmentIntermediateGLR-204Receive and install glass-lined reactor in final positionClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0080EquipmentIntermediateGLR-204Fix and verify GLR bottom valveWork In ProgressCriticalEngineering
Mr.Sharma Ji
2026-07-25YesNo00YesYes
PP-0084EquipmentIntermediateGLR-204Install and fix glass condensing system / condenserReceivedCriticalVendor
Surya Scientific (Vendor)
2026-07-30YesNo00YesYes
PP-0085EquipmentIntermediateGLR-204Execute GLR installation checklist and no-load commissioning trialNot StartedCriticalVendor
HLE Glass Coat (Vendor)
2026-08-05YesNo00YesYes
PP-0087EquipmentClean roomGLR-205Receive and install glass-lined reactor in final positionClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0088EquipmentClean roomGLR-205Fix and verify GLR bottom valveWork In ProgressCriticalEngineering
Mr.Sharma Ji
2026-07-25YesNo00YesYes
PP-0092EquipmentClean roomGLR-205Install and fix glass condensing system / condenserReceivedCriticalVendor
Surya Scientific (Vendor)
2026-07-30YesNo00YesYes
PP-0093EquipmentClean roomGLR-205Execute GLR installation checklist and no-load commissioning trialNot StartedCriticalVendor
HLE Glass Coat (Vendor)
2026-08-05YesNo00YesYes
PP-0095EquipmentClean roomVTD-202Receive VTD at siteClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0099EquipmentClean roomVTD-202Verify solvent trap installation and drain / receiver connectionsNot StartedHighEngineering
Unassigned
No TargetNoNo00YesYes
PP-0101EquipmentClean roomVTD-202Execute empty trial, heating circulation check and vacuum hold testNot StartedCriticalEngineering / Production
Unassigned
No TargetYesNo00YesYes
PP-0103EquipmentIntermediateVTD-201Receive VTD at siteClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0107EquipmentIntermediateVTD-201Verify solvent trap installation and drain / receiver connectionsNot StartedHighEngineering
Unassigned
No TargetNoNo00YesYes
PP-0109EquipmentIntermediateVTD-201Execute empty trial, heating circulation check and vacuum hold testNot StartedCriticalEngineering / Production
Unassigned
No TargetYesNo00YesYes
PP-0119EquipmentIntermediateMilling and sifting areaInstall multi-millNot StartedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0120EquipmentIntermediateMilling and sifting areaInstall sifterNot StartedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0222EquipmentIntermediate / Clean roomCentrifuge 1Verify Centrifuge 1 received at siteClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0223EquipmentIntermediate / Clean roomCentrifuge 1Install Centrifuge 1 in final locationUnder DiscussionCriticalProduction
RD & Production
2026-07-15NoNo00YesYes
PP-0225EquipmentIntermediate / Clean roomCentrifuge 1Execute no-load trial and functional checks for Centrifuge 1Not StartedHighEngineering / Production
Mr.Sharma Ji / Mr.Jain Ji
2026-07-31NoNo00YesYes
PP-0227EquipmentIntermediate / Clean roomCentrifuge 2Verify Centrifuge 2 received at siteClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0228EquipmentIntermediate / Clean roomCentrifuge 2Install Centrifuge 2 in final locationNot StartedCriticalEngineering
Unassigned
No TargetYesNo00YesYes
PP-0230EquipmentIntermediate / Clean roomCentrifuge 2Execute no-load trial and functional checks for Centrifuge 2Not StartedHighEngineering / Production
Unassigned
No TargetNoNo00YesYes
PP-0232EquipmentIntermediateSifterVerify Sifter received at siteClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0233EquipmentIntermediateSifterInstall Sifter in final locationNot StartedCriticalEngineering
Unassigned
No TargetYesNo00YesYes
PP-0235EquipmentIntermediateSifterExecute no-load trial and functional checks for SifterNot StartedHighEngineering / Production
Unassigned
No TargetNoNo00YesYes
PP-0237EquipmentIntermediateMulti-millVerify Multi-mill received at siteClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0238EquipmentIntermediateMulti-millInstall Multi-mill in final locationNot StartedCriticalEngineering
Unassigned
No TargetYesNo00YesYes
PP-0240EquipmentIntermediateMulti-millExecute no-load trial and functional checks for Multi-millNot StartedHighEngineering / Production
Unassigned
No TargetNoNo00YesYes

Imported columns supported: 31. Closed and qualified tasks remain visible unless an open-only filter is selected.