Master Task Register

Filter/search by task code, description, workstream, area, equipment, status, priority, owner, vendor, manual blocker, task dependency, and impact fields. CSV export preserves seed core columns.

Data source: Supabase

Export filtered CSVClear filtersDashboard

Showing Area: Intermediate — 108 of 241 tasks

TaskWorkstreamAreaEquipmentDescriptionStatusPriorityOwnerTargetManual BlockerDependency BlockedBlocked ByBlockingC ImpactQ Impact
PP-0001EquipmentIntermediateSSR-201Receive and install stainless steel reactor in final positionClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0002DocumentationIntermediateSSR-201Receive approved reactor drawings from Amir TanksMaterial AwaitedHighEngineering
Mr.Sharma Ji
2026-07-20YesNo01NoYes
PP-0003EquipmentIntermediateSSR-201Fix and verify reactor bottom valvePO Under ProcessCriticalProcurement
Mr.Kailas
2026-07-16NoYes11YesYes
PP-0004UtilityIntermediateSSR-201Complete vacuum connection to reactorMaterial AwaitedCriticalEngineering / Procurement
Mr.Sharma Ji
2026-07-30YesNo01YesYes
PP-0005Safety / EHSIntermediateSSR-201Complete scrubber / vent connection to reactorVendor MobilizedCriticalVendor
Mr.Reji (Vendor)
2026-07-30YesNo01YesYes
PP-0006UtilityIntermediateSSR-201Complete hot water connection to reactor jacket / coilClosedCriticalEngineering
Mr.Sharma Ji
No TargetNoNo01YesYes
PP-0007EquipmentIntermediateSSR-201Complete reflux lines and interconnecting pipingWork In ProgressCriticalVendor
Amir Tanks
2026-07-22YesNo00YesYes
PP-0008EquipmentIntermediateSSR-201Execute equipment installation checklist and no-load commissioning trialNot StartedCriticalVendor
Amir Tanks
2026-07-30YesYes41YesYes
PP-0009QualificationIntermediateSSR-201Prepare and execute IQ/OQ package for reactorNot StartedHighProduction
Mr.Sharma Ji / Mr.Jain Ji
2026-08-05NoYes10NoYes
PP-0010EquipmentIntermediateSSR-202Receive and install stainless steel reactor in final positionClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0011DocumentationIntermediateSSR-202Receive approved reactor drawings from Amir TanksMaterial AwaitedHighEngineering
Mr.Sharma Ji
2026-07-20YesNo00NoYes
PP-0012EquipmentIntermediateSSR-202Fix and verify reactor bottom valvePO Under ProcessCriticalProcurement
Mr.Kailas
2026-07-16NoNo00YesYes
PP-0013UtilityIntermediateSSR-202Complete vacuum connection to reactorMaterial AwaitedCriticalEngineering / Procurement
Mr.Sharma Ji
2026-07-30YesNo00YesYes
PP-0014Safety / EHSIntermediateSSR-202Complete scrubber / vent connection to reactorVendor MobilizedCriticalVendor
Mr.Reji (Vendor)
2026-07-30YesNo00YesYes
PP-0015UtilityIntermediateSSR-202Complete hot water connection to reactor jacket / coilClosedCriticalEngineering
Mr.Sharma Ji
No TargetNoNo00YesYes
PP-0016EquipmentIntermediateSSR-202Complete reflux lines and interconnecting pipingWork In ProgressCriticalVendor
Amir Tanks
2026-07-22YesNo00YesYes
PP-0017EquipmentIntermediateSSR-202Execute equipment installation checklist and no-load commissioning trialNot StartedCriticalVendor
Amir Tanks
2026-07-30YesNo00YesYes
PP-0018QualificationIntermediateSSR-202Prepare and execute IQ/OQ package for reactorNot StartedHighProduction
Mr.Sharma Ji / Mr.Jain Ji
2026-08-05NoNo00NoYes
PP-0019EquipmentIntermediateSSR-203Receive and install stainless steel reactor in final positionClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0020DocumentationIntermediateSSR-203Receive approved reactor drawings from Amir TanksMaterial AwaitedHighEngineering
Mr.Sharma Ji
2026-07-20YesNo00NoYes
PP-0021EquipmentIntermediateSSR-203Fix and verify reactor bottom valvePO Under ProcessCriticalProcurement
Mr.Kailas
2026-07-16NoNo00YesYes
PP-0022UtilityIntermediateSSR-203Complete vacuum connection to reactorMaterial AwaitedCriticalEngineering / Procurement
Mr.Sharma Ji
2026-07-30YesNo00YesYes
PP-0023Safety / EHSIntermediateSSR-203Complete scrubber / vent connection to reactorVendor MobilizedCriticalVendor
Mr.Reji (Vendor)
2026-07-30YesNo00YesYes
PP-0024UtilityIntermediateSSR-203Complete hot water connection to reactor jacket / coilClosedCriticalEngineering
Mr.Sharma Ji
No TargetNoNo00YesYes
PP-0025EquipmentIntermediateSSR-203Complete reflux lines and interconnecting pipingWork In ProgressCriticalVendor
Amir Tanks
2026-07-22YesNo00YesYes
PP-0026EquipmentIntermediateSSR-203Execute equipment installation checklist and no-load commissioning trialNot StartedCriticalVendor
Amir Tanks
2026-07-30YesNo00YesYes
PP-0027QualificationIntermediateSSR-203Prepare and execute IQ/OQ package for reactorNot StartedHighProduction
Mr.Sharma Ji / Mr.Jain Ji
2026-08-05NoNo00NoYes
PP-0028EquipmentIntermediateSSR-204Receive and install stainless steel reactor in final positionClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0029DocumentationIntermediateSSR-204Receive approved reactor drawings from Amir TanksMaterial AwaitedHighEngineering
Mr.Sharma Ji
2026-07-20YesNo00NoYes
PP-0030EquipmentIntermediateSSR-204Fix and verify reactor bottom valvePO Under ProcessCriticalProcurement
Mr.Kailas
2026-07-16NoNo00YesYes
PP-0031UtilityIntermediateSSR-204Complete vacuum connection to reactorMaterial AwaitedCriticalEngineering / Procurement
Mr.Sharma Ji
2026-07-30YesNo00YesYes
PP-0032Safety / EHSIntermediateSSR-204Complete scrubber / vent connection to reactorVendor MobilizedCriticalVendor
Mr.Reji (Vendor)
2026-07-30YesNo00YesYes
PP-0033UtilityIntermediateSSR-204Complete hot water connection to reactor jacket / coilClosedCriticalEngineering
Mr.Sharma Ji
No TargetNoNo00YesYes
PP-0034EquipmentIntermediateSSR-204Complete reflux lines and interconnecting pipingWork In ProgressCriticalVendor
Amir Tanks
2026-07-22YesNo00YesYes
PP-0035EquipmentIntermediateSSR-204Execute equipment installation checklist and no-load commissioning trialNot StartedCriticalVendor
Amir Tanks
2026-07-30YesNo00YesYes
PP-0036QualificationIntermediateSSR-204Prepare and execute IQ/OQ package for reactorNot StartedHighProduction
Mr.Sharma Ji / Mr.Jain Ji
2026-08-05NoNo00NoYes
PP-0037EquipmentIntermediateSSR-205Receive and install stainless steel reactor in final positionClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0038DocumentationIntermediateSSR-205Receive approved reactor drawings from Amir TanksMaterial AwaitedHighEngineering
Mr.Sharma Ji
2026-07-20YesNo00NoYes
PP-0039EquipmentIntermediateSSR-205Fix and verify reactor bottom valvePO Under ProcessCriticalProcurement
Mr.Kailas
2026-07-16NoNo00YesYes
PP-0040UtilityIntermediateSSR-205Complete vacuum connection to reactorMaterial AwaitedCriticalEngineering / Procurement
Mr.Sharma Ji
2026-07-30YesNo00YesYes
PP-0041Safety / EHSIntermediateSSR-205Complete scrubber / vent connection to reactorVendor MobilizedCriticalVendor
Mr.Reji (Vendor)
2026-07-30YesNo00YesYes
PP-0042UtilityIntermediateSSR-205Complete hot water connection to reactor jacket / coilClosedCriticalEngineering
Mr.Sharma Ji
No TargetNoNo00YesYes
PP-0043EquipmentIntermediateSSR-205Complete reflux lines and interconnecting pipingWork In ProgressCriticalVendor
Amir Tanks
2026-07-22YesNo00YesYes
PP-0044EquipmentIntermediateSSR-205Execute equipment installation checklist and no-load commissioning trialNot StartedCriticalVendor
Amir Tanks
2026-07-30YesNo00YesYes
PP-0045QualificationIntermediateSSR-205Prepare and execute IQ/OQ package for reactorNot StartedHighProduction
Mr.Sharma Ji / Mr.Jain Ji
2026-08-05NoNo00NoYes
PP-0055EquipmentIntermediateGLR-201Receive and install glass-lined reactor in final positionClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0056EquipmentIntermediateGLR-201Fix and verify GLR bottom valveWork In ProgressCriticalEngineering
Mr.Sharma Ji
2026-07-25YesNo00YesYes
PP-0057UtilityIntermediateGLR-201Complete vacuum connection to GLRMaterial AwaitedCriticalProcurement
Mr.Kailas
2026-07-25YesNo00YesYes
PP-0058Safety / EHSIntermediateGLR-201Complete scrubber / vent connection to GLRReceivedCriticalVendor
Mr.Reji (Vendor)
2026-07-25YesNo00YesYes
PP-0059UtilityIntermediateGLR-201Complete hot water connection to GLR jacket / coilClosedCriticalEngineering
Mr.Sharma Ji
No TargetYesNo00YesYes
PP-0060EquipmentIntermediateGLR-201Install and fix glass condensing system / condenserReceivedCriticalVendor
Surya Scientific (Vendor)
2026-07-30YesNo01YesYes
PP-0061EquipmentIntermediateGLR-201Execute GLR installation checklist and no-load commissioning trialNot StartedCriticalVendor
HLE Glass Coat (Vendor)
2026-08-05YesYes11YesYes
PP-0062QualificationIntermediateGLR-201Prepare and execute IQ/OQ package for GLRNot StartedHighProduction
Mr.Sharma Ji / Mr.Jain Ji
2026-08-05YesYes10NoYes
PP-0063EquipmentIntermediateGLR-202Receive and install glass-lined reactor in final positionClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0064EquipmentIntermediateGLR-202Fix and verify GLR bottom valveWork In ProgressCriticalEngineering
Mr.Sharma Ji
2026-07-25YesNo00YesYes
PP-0065UtilityIntermediateGLR-202Complete vacuum connection to GLRMaterial AwaitedCriticalProcurement
Mr.Kailas
2026-07-25YesNo00YesYes
PP-0066Safety / EHSIntermediateGLR-202Complete scrubber / vent connection to GLRReceivedCriticalVendor
Mr.Reji (Vendor)
2026-07-25YesNo00YesYes
PP-0067UtilityIntermediateGLR-202Complete hot water connection to GLR jacket / coilClosedCriticalEngineering
Mr.Sharma Ji
No TargetYesNo00YesYes
PP-0068EquipmentIntermediateGLR-202Install and fix glass condensing system / condenserReceivedCriticalVendor
Surya Scientific (Vendor)
2026-07-30YesNo00YesYes
PP-0069EquipmentIntermediateGLR-202Execute GLR installation checklist and no-load commissioning trialNot StartedCriticalVendor
HLE Glass Coat (Vendor)
2026-08-05YesNo00YesYes
PP-0070QualificationIntermediateGLR-202Prepare and execute IQ/OQ package for GLRNot StartedHighProduction
Mr.Sharma Ji / Mr.Jain Ji
2026-08-05YesNo00NoYes
PP-0071EquipmentIntermediateGLR-203Receive and install glass-lined reactor in final positionClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0072EquipmentIntermediateGLR-203Fix and verify GLR bottom valveWork In ProgressCriticalEngineering
Mr.Sharma Ji
2026-07-25YesNo00YesYes
PP-0073UtilityIntermediateGLR-203Complete vacuum connection to GLRMaterial AwaitedCriticalProcurement
Mr.Kailas
2026-07-25YesNo00YesYes
PP-0074Safety / EHSIntermediateGLR-203Complete scrubber / vent connection to GLRReceivedCriticalVendor
Mr.Reji (Vendor)
2026-07-25YesNo00YesYes
PP-0075UtilityIntermediateGLR-203Complete hot water connection to GLR jacket / coilClosedCriticalEngineering
Mr.Sharma Ji
No TargetYesNo00YesYes
PP-0076EquipmentIntermediateGLR-203Install and fix glass condensing system / condenserReceivedCriticalVendor
Surya Scientific (Vendor)
2026-07-30YesNo00YesYes
PP-0077EquipmentIntermediateGLR-203Execute GLR installation checklist and no-load commissioning trialNot StartedCriticalVendor
HLE Glass Coat (Vendor)
2026-08-05YesNo00YesYes
PP-0078QualificationIntermediateGLR-203Prepare and execute IQ/OQ package for GLRNot StartedHighProduction
Mr.Sharma Ji / Mr.Jain Ji
2026-08-05YesNo00NoYes
PP-0079EquipmentIntermediateGLR-204Receive and install glass-lined reactor in final positionClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0080EquipmentIntermediateGLR-204Fix and verify GLR bottom valveWork In ProgressCriticalEngineering
Mr.Sharma Ji
2026-07-25YesNo00YesYes
PP-0081UtilityIntermediateGLR-204Complete vacuum connection to GLRMaterial AwaitedCriticalProcurement
Mr.Kailas
2026-07-25YesNo00YesYes
PP-0082Safety / EHSIntermediateGLR-204Complete scrubber / vent connection to GLRReceivedCriticalVendor
Mr.Reji (Vendor)
2026-07-25YesNo00YesYes
PP-0083UtilityIntermediateGLR-204Complete hot water connection to GLR jacket / coilClosedCriticalEngineering
Mr.Sharma Ji
No TargetYesNo00YesYes
PP-0084EquipmentIntermediateGLR-204Install and fix glass condensing system / condenserReceivedCriticalVendor
Surya Scientific (Vendor)
2026-07-30YesNo00YesYes
PP-0085EquipmentIntermediateGLR-204Execute GLR installation checklist and no-load commissioning trialNot StartedCriticalVendor
HLE Glass Coat (Vendor)
2026-08-05YesNo00YesYes
PP-0086QualificationIntermediateGLR-204Prepare and execute IQ/OQ package for GLRNot StartedHighProduction
Mr.Sharma Ji / Mr.Jain Ji
2026-08-05YesNo00NoYes
PP-0103EquipmentIntermediateVTD-201Receive VTD at siteClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0104AreaIntermediateVTD-201Complete VTD room civil work: doors, AHU, air pipelines and flooringWork In ProgressCriticalEngineering / HVAC
Unassigned
No TargetYesNo00YesYes
PP-0105UtilityIntermediateVTD-201Complete hot water connection to VTDNot StartedCriticalEngineering
Unassigned
No TargetYesNo00YesYes
PP-0106UtilityIntermediateVTD-201Complete vacuum connection to VTDPO Under ProcessCriticalEngineering / Procurement
Unassigned
No TargetYesNo00YesYes
PP-0107EquipmentIntermediateVTD-201Verify solvent trap installation and drain / receiver connectionsNot StartedHighEngineering
Unassigned
No TargetNoNo00YesYes
PP-0108Electrical / InstrumentationIntermediateVTD-201Verify VTD motor rotation, control panel, earthing, interlocks and instrumentsNot StartedCriticalElectrical / Instrumentation
Unassigned
No TargetYesNo00YesYes
PP-0109EquipmentIntermediateVTD-201Execute empty trial, heating circulation check and vacuum hold testNot StartedCriticalEngineering / Production
Unassigned
No TargetYesNo00YesYes
PP-0110QualificationIntermediateVTD-201Prepare and execute IQ/OQ package for VTDNot StartedHighQA / Validation
Unassigned
No TargetNoNo00NoYes
PP-0119EquipmentIntermediateMilling and sifting areaInstall multi-millNot StartedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0120EquipmentIntermediateMilling and sifting areaInstall sifterNot StartedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0121AreaIntermediateMilling and sifting areaComplete flooring workNot StartedHighEngineering
Unassigned
No TargetNoNo00YesNo
PP-0122Electrical / InstrumentationIntermediateMilling and sifting areaComplete electrical connectionsNot StartedHighElectrical / Instrumentation
Unassigned
No TargetNoNo00YesNo
PP-0123Safety / EHSIntermediateMilling and sifting areaComplete dust extraction / dusting connectionsUnder DiscussionCriticalEngineering / EHS
Unassigned
No TargetYesNo00YesNo
PP-0124AreaIntermediateIntermediate storage areaFix doors and windowsWork In ProgressHighEngineering
Unassigned
No TargetNoNo00YesNo
PP-0125AreaIntermediateIntermediate storage areaComplete flooring workNot StartedHighEngineering
Unassigned
No TargetNoNo00YesNo
PP-0126AreaIntermediatePacking material storage areaFix doors and windowsWork In ProgressHighEngineering
Unassigned
No TargetNoNo00YesNo
PP-0127AreaIntermediateRaw material storage areaFix doors and windowsWork In ProgressHighEngineering
Unassigned
No TargetNoNo00YesNo
PP-0128AreaIntermediateOffice areaComplete office area civil / access readinessWork In ProgressHighEngineering
Unassigned
No TargetNoNo00YesNo
PP-0129Safety / EHSIntermediateMezzanine floorComplete man movement pathwayWork In ProgressCriticalEngineering / EHS
Unassigned
No TargetNoNo00YesNo
PP-0130Safety / EHSIntermediateMezzanine floorComplete ladders for man movementWork In ProgressCriticalEngineering / EHS
Unassigned
No TargetNoNo00YesNo
PP-0131Safety / EHSIntermediateEmergency exitInstall emergency exit doorsWork In ProgressCriticalEngineering / EHS
Unassigned
2026-08-15NoNo00YesYes
PP-0232EquipmentIntermediateSifterVerify Sifter received at siteClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0233EquipmentIntermediateSifterInstall Sifter in final locationNot StartedCriticalEngineering
Unassigned
No TargetYesNo00YesYes
PP-0234Electrical / InstrumentationIntermediateSifterComplete electrical connection, earthing and safety interlock check for SifterNot StartedCriticalElectrical / Instrumentation
Unassigned
No TargetYesNo00YesYes
PP-0235EquipmentIntermediateSifterExecute no-load trial and functional checks for SifterNot StartedHighEngineering / Production
Unassigned
No TargetNoNo00YesYes
PP-0236QualificationIntermediateSifterPrepare and execute IQ/OQ package for SifterNot StartedHighQA / Validation
Unassigned
No TargetNoNo00NoYes
PP-0237EquipmentIntermediateMulti-millVerify Multi-mill received at siteClosedHighEngineering
Unassigned
No TargetNoNo00NoNo
PP-0238EquipmentIntermediateMulti-millInstall Multi-mill in final locationNot StartedCriticalEngineering
Unassigned
No TargetYesNo00YesYes
PP-0239Electrical / InstrumentationIntermediateMulti-millComplete electrical connection, earthing and safety interlock check for Multi-millNot StartedCriticalElectrical / Instrumentation
Unassigned
No TargetYesNo00YesYes
PP-0240EquipmentIntermediateMulti-millExecute no-load trial and functional checks for Multi-millNot StartedHighEngineering / Production
Unassigned
No TargetNoNo00YesYes
PP-0241QualificationIntermediateMulti-millPrepare and execute IQ/OQ package for Multi-millNot StartedHighQA / Validation
Unassigned
No TargetNoNo00NoYes