Pilot Plant TrackerChecking session…

Notification Preview

Preview only. No emails are sent from this page and no send action is available.

As-of date: 2026-09-18 (Asia/Kolkata)

Total open tasks158
Due Today0
Overdue141
Mapped stakeholder127
Unmapped owner58
No responsible person0
Ambiguous mappings0

Notification Preview by Stakeholder

Dharmendra Sharma (d***@thinqcro.com)

Department: Engineering · Due Today: 0 · Overdue: 86

Task codeActivityEquipment/systemStatusEffective due dateDays overduePriorityRemarks / next action
PP-0002Receive approved reactor drawings from Amir TanksSSR-201Material Awaited2026-07-2060HighDrawings received, need to be corrected as per actual
PP-0004Complete vacuum connection to reactorSSR-201Work In Progress2026-07-3050Criticalwork to be started after receipt of material
PP-0009Prepare and execute IQ/OQ package for reactorSSR-201Not Started2026-08-0544HighAmir tanks presence required during qualification
PP-0011Receive approved reactor drawings from Amir TanksSSR-202Material Awaited2026-07-2060HighDrawings received, need to be corrected as per actual
PP-0013Complete vacuum connection to reactorSSR-202Material Awaited2026-07-3050Criticalwork to be started after receipt of material
PP-0018Prepare and execute IQ/OQ package for reactorSSR-202Not Started2026-08-0544HighAmir tanks presence required during qualification
PP-0020Receive approved reactor drawings from Amir TanksSSR-203Material Awaited2026-07-2060HighDrawings received, need to be corrected as per actual
PP-0022Complete vacuum connection to reactorSSR-203Material Awaited2026-07-3050Criticalwork to be started after receipt of material
PP-0027Prepare and execute IQ/OQ package for reactorSSR-203Not Started2026-08-0544HighAmir tanks presence required during qualification
PP-0029Receive approved reactor drawings from Amir TanksSSR-204Material Awaited2026-07-2060HighDrawings received, need to be corrected as per actual
PP-0031Complete vacuum connection to reactorSSR-204Material Awaited2026-07-3050Criticalwork to be started after receipt of material
PP-0036Prepare and execute IQ/OQ package for reactorSSR-204Not Started2026-08-0544HighAmir tanks presence required during qualification
PP-0038Receive approved reactor drawings from Amir TanksSSR-205Material Awaited2026-07-2060HighDrawings received, need to be corrected as per actual
PP-0040Complete vacuum connection to reactorSSR-205Material Awaited2026-07-3050Criticalwork to be started after receipt of material
PP-0045Prepare and execute IQ/OQ package for reactorSSR-205Not Started2026-08-0544HighAmir tanks presence required during qualification
PP-0047Receive approved reactor drawings from Amir TanksSSR-206Material Awaited2026-07-2060HighDrawings received, need to be corrected as per actual
PP-0049Complete vacuum connection to reactorSSR-206Work In Progress2026-07-3050Criticalwork to be started after receipt of material
PP-0054Prepare and execute IQ/OQ package for reactorSSR-206Not Started2026-08-0544HighAmir tanks presence required during qualification
PP-0062Prepare and execute IQ/OQ package for GLRGLR-201Not Started2026-08-0544HighCommissioning planned after completion of all activities
PP-0064Fix and verify GLR bottom valveGLR-202Work In Progress2026-07-2555CriticalReceived, to be installed
PP-0070Prepare and execute IQ/OQ package for GLRGLR-202Not Started2026-08-0544HighCommissioning planned after completion of all activities
PP-0072Fix and verify GLR bottom valveGLR-203Work In Progress2026-07-2555CriticalReceived, to be installed
PP-0078Prepare and execute IQ/OQ package for GLRGLR-203Not Started2026-08-0544HighCommissioning planned after completion of all activities
PP-0080Fix and verify GLR bottom valveGLR-204Work In Progress2026-07-2555CriticalReceived, to be installed
PP-0086Prepare and execute IQ/OQ package for GLRGLR-204Not Started2026-08-0544HighCommissioning planned after completion of all activities
PP-0088Fix and verify GLR bottom valveGLR-205Work In Progress2026-07-2555CriticalReceived, to be installed
PP-0094Prepare and execute IQ/OQ package for GLRGLR-205Not Started2026-08-0544HighCommissioning planned after completion of all activities
PP-0098Complete vacuum connection to VTDVTD-202Work In Progress2026-08-1435Critical
PP-0100Verify VTD motor rotation, control panel, earthing, interlocks and instrumentsVTD-202Not Started2026-08-3118Critical
PP-0101Execute empty trial, heating circulation check and vacuum hold testVTD-202Not Started2026-08-3118Critical
PP-0106Complete vacuum connection to VTDVTD-201Work In Progress2026-08-1435Critical
PP-0108Verify VTD motor rotation, control panel, earthing, interlocks and instrumentsVTD-201Not Started2026-08-3118CriticalAfter completion of all connections
PP-0109Execute empty trial, heating circulation check and vacuum hold testVTD-201Not Started2026-09-153Critical
PP-0111Complete doors and area access readinessWashing areaWork In Progress2026-08-3118High
PP-0115Complete doors and area access readinessPackaging areaWork In Progress2026-08-3118Highwork under progress
PP-0119Install multi-millMilling and sifting areaNot Started2026-08-3118HighMulti Mill received, Intermediate area by 31/08/2026, PP Area completed documentation to be started
PP-0120Install sifterMilling and sifting areaNot Started2026-08-3118HighSifter received, to be installed. clean room sifter installed documentation to be started
PP-0124Fix doors and windowsIntermediate storage areaWork In Progress2026-08-1039HighDoor fixing completed except double doors, awaited for windows material
PP-0126Fix doors and windowsPacking material storage areaWork In Progress2026-08-1435Highwork under progress
PP-0127Fix doors and windowsRaw material storage areaWork In Progress2026-08-3118High
PP-0130Complete ladders for man movementMezzanine floorWork In Progress2026-08-1435Criticalwork under progress
PP-0131Install emergency exit doorsEmergency exitWork In Progress2026-08-1534Criticalcan be installed after completion of work
PP-0149Complete hot water circulation pipeline connections and insulationHot Water SystemWork In Progress2026-07-2852Criticalcompleted for Reactors, pipe line required for completion of VTD
PP-0152Complete line tagging, valve tagging, direction marking and pressure/leak testing for utility manifold - ss reactorsUtility Manifold - SS ReactorsWork In Progress2026-08-3118Critical
PP-0153Update as-built drawing for utility manifold - ss reactorsUtility Manifold - SS ReactorsNot Started2026-08-3118High
PP-0155Complete line tagging, valve tagging, direction marking and pressure/leak testing for utility manifold - gl reactorsUtility Manifold - GL ReactorsWork In Progress2026-08-3118Critical
PP-0158Complete line tagging, valve tagging, direction marking and pressure/leak testing for utility manifold - clean room reactorsUtility Manifold - Clean Room ReactorsWork In Progress2026-08-3118Critical
PP-0162Install low vacuum system piping, headers and equipment take-offsLow Vacuum SystemWork In Progress2026-08-1039Critical
PP-0163Perform low vacuum system leak test and vacuum hold testLow Vacuum SystemNot Started2026-07-1466Critical
PP-0166Install high vacuum system piping, headers and equipment take-offsHigh Vacuum SystemMaterial Awaited2026-07-3050Criticalwork to be started, material awaited
PP-0167Perform high vacuum system leak test and vacuum hold testHigh Vacuum SystemNot Started2026-07-3050Critical
PP-0168Verify scrubber installation completionScrubber SystemWork In Progress2026-08-1435High
PP-0169Start and complete scrubber piping worksScrubber SystemWork In Progress2026-08-1435Critical
PP-0170Commission scrubber: circulation pump, blower/fan, media, drain and vent flow verificationScrubber SystemWork In Progress2026-08-1435Critical
PP-0176Perform air balancing and room pressure differential verificationHVAC SystemNot Started2026-09-0711CriticalAfter completion of All HVAC installation works
PP-0177Verify temperature and RH performanceHVAC SystemNot Started2026-09-0711HighIt will be performed during Clean Room area qualification
PP-0178Perform particle count and area classificationHVAC SystemNot Started2026-09-0711CriticalIt will be performed during Clean room area qualification
PP-0180Perform clean room cleaning and QA/EHS area releaseClean Room AreaWork In Progress2026-08-1039Criticalcivil, electrical, fabrication works under progress
PP-0182Complete general lighting worksElectrical DistributionWork In Progress2026-07-3149Highwork to be started after completion of ducting work
PP-0183Install and verify emergency lightingElectrical DistributionWork In Progress2026-07-3050Criticalwork to be started after completion of ducting work
PP-0185Perform motor direction checks for all rotating equipmentElectrical DistributionWork In Progress2026-07-3149HighSS Reactors completed, Glass Lined Reactors to be verified after commissioning
PP-0186Calibrate temperature, pressure and vacuum instrumentsInstrumentationNot Started2026-08-3118HighDuring equipment qualification
PP-0189Complete hydrogenation area utility pipeline workHydrogenation AreaWork In Progress2026-08-1534Criticalworks under progress
PP-0194Install hydrogen and nitrogen manifold with tagged valves and regulatorsHydrogen / Nitrogen ManifoldNot Started2026-08-1435Criticaldelivery will takes 2-3 weeks
PP-0195Perform pressure test, leak test and purge verification for gas manifoldHydrogen / Nitrogen ManifoldNot Started2026-08-2029CriticalTesting can be performed after completion of installation
PP-0196Verify flameproof electrical fittings, earthing and bondingHydrogenation AreaNot Started2026-08-1039Criticalwork to be started
PP-0197Install/verify hydrogen gas detection and ventilationHydrogenation AreaNot Started2026-08-3118Criticalwork to be started
PP-0201Prepare and execute IQ/OQ package for hydrogen reactorHydrogen Reactor 250 LNot Started2026-08-3118CriticalQualification can be performed after completion of all activities
PP-0202Obtain detailed area layout drawing from AtkaraniArea & GMP LayoutWork In Progress2026-08-3118CriticalCritical gap from planning discussion.
PP-0206Prepare waste movement flow and emergency exit mapArea & GMP LayoutWork In Progress2026-08-2029CriticalCritical gap from planning discussion.
PP-0207Approve and display final GMP layout at siteArea & GMP LayoutNot Started2026-08-3118CriticalCritical gap from planning discussion.
PP-0210Complete calibration certificates for critical instrumentsCalibration PackNot Started2026-08-1039HighEngineering / QA work together
PP-0219Release PO and mobilize insulation vendor for chilled/brine/hot water/steam insulationInsulation PackageWork In Progress2026-07-3149Criticalwork under progress
PP-0224Complete electrical connection, earthing and safety interlock check for Centrifuge 1Centrifuge 1Work In Progress2026-08-1435Criticalwork under progress
PP-0225Execute no-load trial and functional checks for Centrifuge 1Centrifuge 1Not Started2026-07-3149High
PP-0226Prepare and execute IQ/OQ package for Centrifuge 1Centrifuge 1Not Started2026-08-0544HighAfter completion of installation & connections
PP-0229Complete electrical connection, earthing and safety interlock check for Centrifuge 2Centrifuge 2Not Started2026-07-3050CriticalElectrical and other works to be started
PP-0230Execute no-load trial and functional checks for Centrifuge 2Centrifuge 2Not Started2026-08-0544HighNo load trial after completion of commissioning
PP-0231Prepare and execute IQ/OQ package for Centrifuge 2Centrifuge 2Not Started2026-08-1435HighAfter completion of Successful trial run
PP-0233Install Sifter in final locationSifterWork In Progress2026-08-1435Critical
PP-0235Execute no-load trial and functional checks for SifterSifterNot Started2026-08-1435High
PP-0236Prepare and execute IQ/OQ package for SifterSifterNot Started2026-08-3118High
PP-0238Install Multi-mill in final locationMulti-millNot Started2026-08-1435CriticalMulti Mill received, to be installed
PP-0239Complete electrical connection, earthing and safety interlock check for Multi-millMulti-millNot Started2026-08-1435CriticalReceived, to be installed. Electrical connection work completed
PP-0240Execute no-load trial and functional checks for Multi-millMulti-millNot Started2026-08-1435HighReceived, to be installed. Electrical connection work completed
PP-0241Prepare and execute IQ/OQ package for Multi-millMulti-millNot Started2026-09-153HighQualification to be started after installation

Kailas (k***@thinqcro.com)

Department: Procurement · Due Today: 0 · Overdue: 38

Task codeActivityEquipment/systemStatusEffective due dateDays overduePriorityRemarks / next action
PP-0005Complete scrubber / vent connection to reactorSSR-201Vendor Mobilized2026-07-3050CriticalMaterial received, work to be started
PP-0008Execute equipment installation checklist and no-load commissioning trialSSR-201Not Started2026-07-3050Criticalwaiting for Amir tanks Team, awaiting for documents
PP-0014Complete scrubber / vent connection to reactorSSR-202Vendor Mobilized2026-07-3050CriticalMaterial received, work to be started
PP-0017Execute equipment installation checklist and no-load commissioning trialSSR-202Not Started2026-07-3050Criticalwaiting for Amir tanks Team, awaiting for documents
PP-0023Complete scrubber / vent connection to reactorSSR-203Vendor Mobilized2026-07-3050CriticalMaterial received, work to be started
PP-0026Execute equipment installation checklist and no-load commissioning trialSSR-203Not Started2026-07-3050Criticalwaiting for Amir tanks Team, awaiting for documents
PP-0032Complete scrubber / vent connection to reactorSSR-204Vendor Mobilized2026-07-3050CriticalMaterial received, work to be started
PP-0035Execute equipment installation checklist and no-load commissioning trialSSR-204Not Started2026-07-3050Criticalwaiting for Amir tanks Team, awaiting for documents
PP-0041Complete scrubber / vent connection to reactorSSR-205Vendor Mobilized2026-07-3050CriticalMaterial received, work to be started
PP-0043Complete reflux lines and interconnecting pipingSSR-205Work In Progress2026-07-2258Criticalwaiting for Amir tanks team
PP-0044Execute equipment installation checklist and no-load commissioning trialSSR-205Not Started2026-07-3050Criticalwaiting for Amir tanks Team, awaiting for documents
PP-0050Complete scrubber / vent connection to reactorSSR-206Vendor Mobilized2026-07-3050CriticalMaterial received, work to be started
PP-0052Complete reflux lines and interconnecting pipingSSR-206Work In Progress2026-07-2258Criticalwaiting for Amir tanks team
PP-0053Execute equipment installation checklist and no-load commissioning trialSSR-206Not Started2026-07-3050Criticalwaiting for Amir tanks Team, awaiting for documents
PP-0057Complete vacuum connection to GLRGLR-201Work In Progress2026-07-2555Criticalwork to be started after receipt by 15/07/2026
PP-0058Complete scrubber / vent connection to GLRGLR-201Work In Progress2026-07-2555Criticalwork to be started from 15/07/2026
PP-0060Install and fix glass condensing system / condenserGLR-201Work In Progress2026-07-3050CriticalPlanned from next week from 20/07/2026
PP-0065Complete vacuum connection to GLRGLR-202Material Awaited2026-07-2555Criticalwork to be started after receipt by 15/07/2026
PP-0066Complete scrubber / vent connection to GLRGLR-202Received2026-07-2555Criticalwork to be started from 15/07/2026
PP-0068Install and fix glass condensing system / condenserGLR-202Received2026-07-3050CriticalPlanned from next week from 20/07/2026
PP-0069Execute GLR installation checklist and no-load commissioning trialGLR-202Not Started2026-08-0544Criticalwaiting for completion of utility and other activities
PP-0073Complete vacuum connection to GLRGLR-203Material Awaited2026-07-2555Criticalwork to be started after receipt by 15/07/2026
PP-0074Complete scrubber / vent connection to GLRGLR-203Received2026-07-2555Criticalwork to be started from 15/07/2026
PP-0076Install and fix glass condensing system / condenserGLR-203Received2026-07-3050CriticalPlanned from next week from 20/07/2026
PP-0077Execute GLR installation checklist and no-load commissioning trialGLR-203Not Started2026-08-0544Criticalwaiting for completion of utility and other activities
PP-0081Complete vacuum connection to GLRGLR-204Material Awaited2026-07-2555Criticalwork to be started after receipt by 15/07/2026
PP-0082Complete scrubber / vent connection to GLRGLR-204Received2026-07-2555Criticalwork to be started from 15/07/2026
PP-0084Install and fix glass condensing system / condenserGLR-204Received2026-07-3050CriticalPlanned from next week from 20/07/2026
PP-0085Execute GLR installation checklist and no-load commissioning trialGLR-204Not Started2026-08-0544Criticalwaiting for completion of utility and other activities
PP-0089Complete vacuum connection to GLRGLR-205Material Awaited2026-07-2555Criticalwork to be started after receipt by 15/07/2026
PP-0090Complete scrubber / vent connection to GLRGLR-205Received2026-07-2555Criticalwork to be started from 15/07/2026
PP-0092Install and fix glass condensing system / condenserGLR-205Received2026-07-3050CriticalPlanned from next week from 20/07/2026
PP-0093Execute GLR installation checklist and no-load commissioning trialGLR-205Not Started2026-08-0544Criticalwaiting for completion of utility and other activities
PP-0098Complete vacuum connection to VTDVTD-202Work In Progress2026-08-1435Critical
PP-0150Commission hot water system and verify temperature / circulation performanceHot Water SystemNot Started2026-07-3149CriticalInstallation completed, commissioning activity by Amir Tanks
PP-0168Verify scrubber installation completionScrubber SystemWork In Progress2026-08-1435High
PP-0193Issue PO and receive hydrogen / nitrogen manifold materialsHydrogen / Nitrogen ManifoldUnder Discussion2026-07-2456CriticalUnder discussions and finalization
PP-0200Execute hydrogen reactor commissioning trialHydrogen Reactor 250 LNot Started2026-08-1039CriticalAfter completion of other activities

Siva (s***@thinqcro.com)

Department: Production · Due Today: 0 · Overdue: 7

Task codeActivityEquipment/systemStatusEffective due dateDays overduePriorityRemarks / next action
PP-0128Complete office area civil / access readinessOffice areaWork In Progress2026-08-1435Highwork under progress
PP-0132Finalize emergency exit locationEmergency exitUnder Discussion2026-07-2060CriticalIdentified one of the area, to be finalized
PP-0144Perform temperature achievement, circulation and load verification for chilled brine plantChilled Brine PlantWork In Progress2026-07-3149Highdate to be confirmed by vendor
PP-0191Obtain quote for hydrogen manifoldHydrogen / Nitrogen ManifoldQuote Awaited2026-07-2060CriticalQuote received from PCI, awaited for another quote
PP-0192Obtain quote for nitrogen manifoldHydrogen / Nitrogen ManifoldQuote Awaited2026-07-2060CriticalQuote received from PCI, awaited for another quote
PP-0193Issue PO and receive hydrogen / nitrogen manifold materialsHydrogen / Nitrogen ManifoldUnder Discussion2026-07-2456CriticalUnder discussions and finalization
PP-0201Prepare and execute IQ/OQ package for hydrogen reactorHydrogen Reactor 250 LNot Started2026-08-3118CriticalQualification can be performed after completion of all activities

Suppressed Stakeholders

Stakeholders with notification_enabled=false are shown here and excluded from notification preview totals.

No tasks.

Unmapped Owner Report

Responsible person raw valueNormalized fragmentsTask countAffected task codesSuggested administrative action
Mr.Sharma Ji / Mr.Jain Jisharma, jain20PP-0009, PP-0018, PP-0027, PP-0036, PP-0045, PP-0054, PP-0062, PP-0070, PP-0078, PP-0086, PP-0094, PP-0119, PP-0120, PP-0152, PP-0195, PP-0225, PP-0226, PP-0231, PP-0238, PP-0239Create stakeholder or add alias
Pradham HVACpradham hvac7PP-0096, PP-0104, PP-0112, PP-0116, PP-0172, PP-0173, PP-0174Create stakeholder or add alias
Mr.Sharma Ji / Vendorsharma, vendor9PP-0106, PP-0115, PP-0130, PP-0131, PP-0162, PP-0176, PP-0178, PP-0194, PP-0230Create stakeholder or add alias
Mr.Sharma Ji / JITsharma, jit1PP-0124Create stakeholder or add alias
Mr.Vishalvishal1PP-0133Create stakeholder or add alias
Mr.Sulkasulka1PP-0138Create stakeholder or add alias
Mr.Suklasukla1PP-0139Create stakeholder or add alias
Mr.Sharma / Mr.Jainsharma, jain7PP-0155, PP-0158, PP-0206, PP-0207, PP-0236, PP-0240, PP-0241Create stakeholder or add alias
Mr.Sharma / Vendorsharma, vendor2PP-0169, PP-0170Create stakeholder or add alias
Mr.Jainjain1PP-0171Create stakeholder or add alias
Mr.Sharma Ji / Pradham (Vendor)sharma, pradham vendor2PP-0177, PP-0180Create stakeholder or add alias
JIT / Vendorjit, vendor1PP-0179Create stakeholder or add alias
Sri Ram Enterprisessri ram enterprises1PP-0190Create stakeholder or add alias
Mr.Nikhil sir / Mr.Jain / Mr.Bagalnikhil sir, jain, bagal1PP-0198Create stakeholder or add alias
Mr.Siva / Mr.Jain Ji / Mr.Sharma JIsiva, jain, sharma1PP-0201Create stakeholder or add alias
Mr.Sharma Ji/ Mr.Bhishama Jisharma, bhishama1PP-0210Create stakeholder or add alias
Mr.Sharma Ji / Ravi Insulationsharma, ravi insulation1PP-0219Create stakeholder or add alias

Ambiguous Owner Report

No issues.

Tasks without responsible person

No tasks.

Tasks without effective due date

TaskActivityResponsible personEffective due date
PP-0156Update as-built drawing for utility manifold - gl reactorsMr.Sharma
PP-0159Update as-built drawing for utility manifold - clean room reactorsMr.Sharma
PP-0187Test alarms, interlocks and emergency stopsMr.Sharma Ji / Vendor
PP-0199Complete EHS pre-startup safety review for hydrogenationProduction / Safety
PP-0208Compile approved P&IDs and as-built utility/equipment drawingsMr.Sharma
PP-0209Collect vendor manuals, MOCs, certificates and commissioning checklistsMr.Sharma Ji / Vendor
PP-0211Compile leak test, pressure test and vacuum hold recordsMr.Sharma Ji / Mr.Jain Ji
PP-0212Prepare IQ protocols for all critical equipment and utilitiesAmir Tanks
PP-0213Prepare OQ protocols for all critical equipment and utilitiesMr.Jain
PP-0214Prepare SOPs for operation, cleaning, safety and emergency handlingMr.Jain Ji
PP-0215Create preventive maintenance plan and lubrication checklistMr.Sharma
PP-0216Complete operator and maintenance team trainingMr.Jain / Mr.Bagal
PP-0217Complete pre-startup safety review and final EHS clearanceMr.Jain / Mr.Bagal / Mr.Vishal
PP-0218Conduct final QA/Engineering/Production handover and ready-to-operate approvalMr.Jain / Mr.Sharma / Mr.Bagal
PP-0221Complete dependency mapping and downstream impact reviewNick